Battery storage planning approval rates by council

UK planning authorities have decided 1,744 battery storage schemes and approved 92% of them, taking a median of 6 months. 81,715 MW consented, with 693 applications still awaiting a decision. Computed from recorded outcomes — not modelled.

92%
Approval rate
1,603 of 1,744 decided
6 mo
Median decision
application to decision
81.7 GW
Consented
301 authorities
693
Awaiting decision
live applications

Screen a specific site →

✅ Most permissive

1North Yorkshire100%29 decided
2Somerset100%23 decided
3The Planning Inspectorate - National Infrastructure100%19 decided
4King's Lynn and West Norfolk100%15 decided
5Shropshire100%15 decided
6Rotherham100%14 decided
7Northumberland100%12 decided
8South Norfolk100%12 decided
9Wychavon100%12 decided
10Cumberland100%11 decided

🚧 Least permissive

1Bedford42%12 decided
2East Devon59%17 decided
3North East Derbyshire60%10 decided
4North Somerset60%10 decided
5South Lanarkshire · Scotland60%10 decided
6South Oxfordshire75%8 decided
7Welsh Government (NSIP) · Wales80%15 decided
8North Northamptonshire80%10 decided
9Milton Keynes82%28 decided
10Buckinghamshire82%11 decided

⚡ Fastest to decide

1North Devon1.5 mo5 decided
2Milton Keynes1.8 mo28 decided
3Ipswich1.8 mo9 decided
4Falkirk · Scotland1.8 mo8 decided
5Medway1.8 mo7 decided
6Babergh1.8 mo5 decided
7Redcar and Cleveland1.8 mo5 decided
8Bolsover1.9 mo6 decided
9Bristol, City of2.3 mo8 decided
10Pembrokeshire · Wales2.4 mo12 decided

🐌 Slowest to decide

1The Planning Inspectorate - National Infrastructure17.4 mo19 decided
2Scottish Government (S36) · Scotland17.3 mo108 decided
3Welsh Government (NSIP) · Wales16.7 mo15 decided
4Wiltshire13.9 mo30 decided
5Highland · Scotland12.6 mo34 decided
6Dumfries and Galloway · Scotland12.6 mo13 decided
7Solihull12.6 mo8 decided
8Rushcliffe11.2 mo8 decided
9Leeds10.7 mo8 decided
10North Yorkshire10.5 mo29 decided

📊 Busiest by caseload

1Scottish Government (S36) · Scotland10894%
2Highland · Scotland3485%
3Wiltshire3097%
4North Yorkshire29100%
5Milton Keynes2882%
6Aberdeenshire · Scotland2796%
7Cornwall2596%
8Somerset23100%
9Fife · Scotland2396%
10South Staffordshire2291%

What is the average battery storage scheme approval rate in the UK?

Across 301 UK planning authorities, 92% of decided battery storage schemes applications were approved — 1,603 granted against 141 refused, from 1,744 decisions in total. That is computed from recorded outcomes in the government Renewable Energy Planning Database, not estimated. 81,715 MW has been consented, with 693 applications still awaiting a decision.

How long does battery storage scheme planning permission take?

The median UK authority decides a battery storage scheme application in 6 months, measured from the submission date to the decision date recorded in REPD. The spread is wide: the fastest authorities here decide in around 1.5 months, while the slowest take 17.4 months or more. Speed and approval rate are largely independent — a permissive council is not necessarily a fast one.

Which councils approve the most battery storage schemes?

By volume, Scottish Government (S36), Highland, Wiltshire have decided the most. By approval rate among authorities with a meaningful caseload, North Yorkshire (100%), Somerset (100%), The Planning Inspectorate - National Infrastructure (100%) lead. Every authority with 5 or more decisions is listed below with its own page.

What does this data not tell me?

REPD records outcomes but not refusal REASONS, so nothing here explains why a scheme failed — landscape and cumulative impact, the most common real drivers of refusal, are professional judgements that appear in no open dataset. It covers schemes of roughly 150 kW and above, is published quarterly, and small caseloads make percentages volatile. Use it to compare authorities and set expectations, not to predict an individual decision.

All 137 authorities with 5+ battery storage decisions

Aberdeen CityAberdeenshireAngusAntrim and NewtownabbeyArgyll and ButeAshfordBaberghBarnsleyBasildonBasingstoke and DeaneBassetlawBedfordBlabyBolsoverBoltonBradfordBraintreeBristol, City ofBuckinghamshireCalderdaleCarmarthenshireCentral BedfordshireChelmsfordCherwellCheshire West and ChesterColchesterCornwallCounty DurhamCumberlandDartfordDoncasterDorsetDumfries and GallowayDundee CityEast AyrshireEast CambridgeshireEast DevonEast HertfordshireEast Riding of YorkshireEast SuffolkFalkirkFenlandFifeHartHerefordshire, County ofHigh PeakHighlandHorshamIpswichKing's Lynn and West NorfolkLancasterLeedsLiverpoolMedwayMid SuffolkMid UlsterMilton KeynesMorayNew ForestNewark and SherwoodNewcastle upon TyneNewportNorth AyrshireNorth DevonNorth East DerbyshireNorth East LincolnshireNorth HertfordshireNorth KestevenNorth NorfolkNorth NorthamptonshireNorth SomersetNorth WarwickshireNorth YorkshireNorthumberlandOldhamPembrokeshirePerth and KinrossPeterboroughRedcar and ClevelandRenfrewshireRhondda Cynon TafRochdaleRotherhamRugbyRushcliffeSandwellScottish Government (S36)SheffieldShropshireSolihullSomersetSouth DerbyshireSouth GloucestershireSouth HamsSouth HollandSouth KestevenSouth LanarkshireSouth NorfolkSouth OxfordshireSouth StaffordshireStaffordshire MoorlandsStockportStockton-on-TeesStratford-on-AvonSunderlandSwaleSwanseaSwindonTamesideTelford and WrekinTest ValleyTewkesburyThanetThe Planning Inspectorate - National InfrastructureThurrockTorridgeTraffordTunbridge WellsUttlesfordVale of White HorseWakefieldWarwickWealdenWelsh Government (NSIP)Welwyn HatfieldWest BerkshireWest LancashireWest LothianWest NorthamptonshireWest OxfordshireWest SuffolkWestmorland and FurnessWiltshireWinchesterWrexhamWychavonYork

Other technologies

Solar approval ratesOnshore wind approval rates

Source: Renewable Energy Planning Database (DESNZ, OGL v3.0), 2026 Q1 extract. Approval rate counts decided applications only (approved ÷ approved+refused); withdrawn and undecided are excluded, and a permission later expired still counts as approved because consent was granted. "Least permissive" and "slowest" are limited to authorities with 8+ decisions so a single refusal cannot top the table. REPD covers schemes of roughly 150 kW and above and does not record refusal reasons.