Renewable planning › Battery storage › Stratford-on-Avon
Battery storage planning in Stratford-on-Avon
Stratford-on-Avon has decided 8 battery storage schemes and approved 88% of them, taking a median of 5.3 months to decide. 2 applications still awaiting a decision.
How Stratford-on-Avon compares
Against the 137 UK authorities with 5+ battery storage decisions, Stratford-on-Avon sits in the 29th percentile for approval rate (4 points below the England average) and the 57th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (11)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Dadglow Farm, Bishops Itchington - Battery Energy Storage System Root Power (South) Limited · 24/02516/FUL · 4.1 mo to decide | 20 | Application Refused | 2025-02-06 |
Birmingham And Solihull Rugby Club, Forshaw Heath Lane - Solar Panels Birmingham & Solihull Rugby Football Club · 24/03248/FUL | — | Application Submitted | 2025-02-05 |
Bishops Bowl Fishery - Battery Energy Storage Mercia Power Response · 23/01718/FUL · 2.8 mo to decide | — | Awaiting Construction | 2023-10-06 |
Middle Road Farm - Solar Farm & Battery Storage Leicestershire Solar 1 Limited /Novergy · 23/01305/FUL · 3.4 mo to decide | — | Awaiting Construction | 2023-08-18 |
Sherbourne - Solar Farm Namene Solar · W/23/0150 · 6.4 mo to decide | — | Awaiting Construction | 2023-08-16 |
Crimscote Solar Farm and Storage Project Regener8 SPV1 Limited · 21/02017/FUL · 17.4 mo to decide | — | Under Construction | 2022-11-29 |
Middle Road Farm - Solar Farm & Battery Storage Leicestershire Solar 1 Limited · 22/00001/FUL · 9.8 mo to decide | — | Revised | 2022-10-28 |
Ashorne Hill - Solar Farm JBM Solar Projects Limited · W/21/1801 · 10.3 mo to decide | — | Awaiting Construction | 2022-08-03 |
Eastfields Farm, Harbury - Battery Storage Vantage RE · 21/02448/FUL · 2.8 mo to decide | — | Under Construction | 2021-10-21 |
Radford Solar Farm - energy storage Anesco · 17/01783/FUL | — | Abandoned | 2017-06-14 |
Jaguar Land Rover Kingsway Battery Jaguar Land Rover · 15/03646/FUL | — | Planning Permission Expired | 2015-12-04 |
Does Stratford-on-Avon approve battery storage schemes?
Yes — of the 8 battery storage schemes Stratford-on-Avon has decided, 88% were approved (7 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Stratford-on-Avon?
The median time from application to decision is 5.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Stratford-on-Avon consented?
0 MW has been consented across 7 approved schemes, with 20 MW refused. A further 2 applications awaits a decision.
Other technologies in Stratford-on-Avon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com