Battery storage planning in Highland

Highland has decided 34 battery storage schemes and approved 85% of them, taking a median of 12.6 months to decide. Consented capacity: 808 MW. 7 applications still awaiting a decision.

85%
Approved
29 granted · 5 refused
12.6 mo
Median decision
UK 6 mo
808 MW
Consented
105 MW refused
3
Appeals
3 allowed on appeal

How Highland compares

Against the 137 UK authorities with 5+ battery storage decisions, Highland sits in the 20th percentile for approval rate (7 points below the England average) and the 7th percentile for speed.

Decisions by year

815Approved — 1 (2020)120Approved — 1 (2021)121Approved — 4 (2022)Refused — 1 (2022)522Approved — 3 (2023)Refused — 1 (2023)423Approved — 4 (2024)Refused — 2 (2024)624Approved — 11 (2025)Refused — 1 (2025)1225Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (44)

SchemeMWStatusDecided
Buckies Farm - Battery Energy Storage
OPDE UK Limted · 25/02087/FUL
49.9Application Submitted2026-02-05
Grigorhill Cottage, Grigorhill - Battery Energy Storage
OPDE UK Limted · 25/00154/FUL · 11.1 mo to decide
49.9Awaiting Construction2026-01-13
Cnoc Farasd Wind Farm
E Power Limited · 25/04604/FUL
15Application Submitted2025-12-04
Tigh Na Bradhan, Fasnakyle - Battery Storage Facility
Intelligent Land Investments Group · 23/02133/SP56 · 25.2 mo to decide
Application Refused2025-10-20
Blackpark House - Battery Storage
Anesco · 24/05019/FUL · 9.9 mo to decide
30Awaiting Construction2025-10-14
Geiselittle Farm - Battery Energy Storage
Whirlwind Renewables · 24/03500/FUL · 11.9 mo to decide
49.9Awaiting Construction2025-08-20
Lythmore House, Technology Park Forss - Battery Energy Storage
Forss Energy Storage Limited · 24/04585/FUL · 9 mo to decide
49.9Awaiting Construction2025-08-13
Shore Street - Battery Energy Storage
Inverness Harbour Trust · 24/04909/FUL · 5.9 mo to decide
Awaiting Construction2025-06-10
Balblair Quarry, Balblair - Battery Energy Storeage System
Lovat Estates Limited (LG-B-50a Limited) · 24/01548/FUL · 13.3 mo to decide
49.9Awaiting Construction2025-05-30
Glengolly Farmhouse- Battery Energy Storage
Ecocel Energy Storage Limited · 24/00561/FUL · 12.8 mo to decide
49.9Awaiting Construction2025-04-01
Spittal Mains Quarry - Battery storage
Fig Power Limited · 24/02827/FUL · 8.4 mo to decide
49.9Awaiting Construction2025-03-28
Mybster Croft, Spittal - Battery Energy Storage Facility
Potencia Energy Limited · 23/05424/FUL · 15.6 mo to decide
Awaiting Construction2025-03-19
Invershin Community Hall - Wind Farm & Battery Storage
Garvary Wind Farm Limited · ECU00003251 · 46 mo to decide
Awaiting Construction2025-02-13
Hill Of Lynchrobbie, Dunbeath - Battery Storage Facility
E Power Limited · 25/00107/FUL
5Application Submitted2025-02-03
Dounreay, Thurso - Battery Energy Storage
Ylem Energy Limited (Reay Power) · 24/01669/FUL · 8.4 mo to decide
34Under Construction2025-01-31
The Smithy - Battery Storage
Renewable Energy Systems · 23/05999/FUL · 12.8 mo to decide
45Awaiting Construction2025-01-29
Caulternich Croft Energy Storage Project - Battery Storage Facility
Whirlwind Renewables · 23/03113/FUL · 17.6 mo to decide
49.9Application Refused2024-12-17
Castletown - Wind Farm
Wind 2 Limited · 24/04932/FUL
12Application Submitted2024-12-12
Drumore Cottage, Swordale - Battery Storage
Fig Power · 23/02840/FUL · 17.7 mo to decide
49.9Awaiting Construction2024-12-10
Loch Toftingall, Halsary Wind Farm - Battery Energy Storage
Infinergy Limited / Boralex · 23/04690/FUL · 13.5 mo to decide
49.9Awaiting Construction2024-11-12
Lochluichart - Energy Storage Facility
Intelligent Land Investments Group · 23/05905/FUL · 9.2 mo to decide
49.9Awaiting Construction2024-11-07
Lochend Holding, Barrock - Wind Farm
Constantine Group Limited · 24/02641/FUL
10Application Submitted2024-07-26
Fairways Business Park - Battery Storage
Inverness Caledonian Thistle Football Club · 23/00497/FUL · 13.8 mo to decide
50Application Refused2024-04-11
Cairnview, Bettyhill
Bettyhill 2 Wind Limited · 23/00142/FUL · 13.5 mo to decide
Awaiting Construction2024-02-26
Alness Grid Sub Station, Mid Balnacraig - Battery Storage Facility
Balnacraig Battery Storage Limited · 22/05167/FUL · 12.6 mo to decide
50Awaiting Construction2023-12-11
Raigmore Hospital, Old Perth Road - Battery Storage
NHS Highland · 23/04285/CLP · 1.9 mo to decide
Awaiting Construction2023-11-23
Kintradwell Lodge - Wind Farm & Battery storage
Renewable Energy System Limited · 21/00826/S36 · 32.4 mo to decide
Application Refused2023-11-03
Househill House, Househill - Battery Storage
Whirlwind Energy Storage Limited · 22/03638/FUL · 5.5 mo to decide
49.9Awaiting Construction2023-02-15
Torr Leathann, Ardross - Battery Storage
Energiekontor · 22/02442/FUL · 5.7 mo to decide
5Application Refused2022-11-28
Stainland Energy Storage Project
Whirlwind Energy Storage Limited · 22/02054/FUL · 5.4 mo to decide
49.9Awaiting Construction2022-11-04
Platchaig House, Kilmorack - Battery Storage Facility
Whirlwind Renewables · 21/03353/FUL · 13.5 mo to decide
49.9Revised2022-08-30
Slickly Wind Farm
Statkraft Wind UK Limited · 19/05624/FUL · 31.5 mo to decide
Awaiting Construction2022-08-23
Hillcrest Cottage, Shebster - Battery Energy Storage System
Statkraft UK Limited · 21/05467/FUL · 8 mo to decide
19.9Awaiting Construction2022-08-22
Boat of Garten - Battery Energy Storage
Whirlwind Energy Storage Limited · 22/00601/FUL
49.9Application Withdrawn2022-02-28
Strathrory Wind Farm
Energiekontor UK · 20/00584/FUL · 22.1 mo to decide
Awaiting Construction2022-01-07
Torrdhuin, Auchteraw Battery Storage Facility
Field Energy · 20/04565/FUL · 3.6 mo to decide
49.9Operational2021-03-09
Blackpark Energy Storage
Shires Hamilton · 20/02589/FUL · 5.1 mo to decide
30Awaiting Construction2020-12-15
Auchteraw Energy Storage
Shires Hamilton · 19/05385/FUL
20Application Withdrawn2020-06-29
Kerrow Farm
Shires Hamilton · 19/00704/FUL
20Application Withdrawn2019-06-12
Blackpark Farm
Shires Hamilton · 19/00702/FUL
20Revised2019-02-28
Horse Island Microgrid Project
Wind & Sun
Operational
Isle of Rum Microgrid Project
Wind & Sun
Operational
Isle of Muck Microgrid System
Wind & Sun
Operational
Isle of Eigg Electrification Project
Eigg Electric
0.1Operational

Does Highland approve battery storage schemes?

Yes — of the 34 battery storage schemes Highland has decided, 85% were approved (29 granted, 5 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Highland?

The median time from application to decision is 12.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Highland consented?

808 MW has been consented across 29 approved schemes, with 105 MW refused. A further 7 applications awaits a decision.

Other technologies in Highland

Solar in HighlandOnshore wind in Highland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report