Novarly ParcelRenewable planning

Renewable planning Battery storageNorth Hertfordshire

Battery storage planning in North Hertfordshire

North Hertfordshire has decided 6 battery storage schemes and approved 100% of them, taking a median of 20.3 months to decide. Consented capacity: 26 MW. 5 applications still awaiting a decision.

100%
Approved
6 granted · 0 refused
20.3 mo
Median decision
UK 6 mo
26 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How North Hertfordshire compares

Against the 137 UK authorities with 5+ battery storage decisions, North Hertfordshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 0th percentile for speed.

Decisions by year

35Approved — 2 (2024)224Approved — 3 (2025)325
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Westfield Conservation Park - Battery Energy Storage System
Lightrock Power Limited · 25/01947/FP
99Application Submitted2025-08-05
St Ippolyts - Solar Farm & Battery Storage
Brockwell Storage & Solar Limited · 24/02455/FP · 48 mo to decide
12.5Awaiting Construction2025-07-28
Wandon End - Solar Farm & Battery Storage
EPL 002 Limited · 22/03231/FP · 30.3 mo to decide
Awaiting Construction2025-07-15
Newnham Road, Newnham - Battery Energy Storage
Balance Power Projects Limited · 24/02713/FP · 6.4 mo to decide
Awaiting Construction2025-06-25
Stevenage Road, Titmore Green - Battery Energy Storage System
Pivoted Power Llp · 25/01349/FP
57Application Submitted2025-05-20
Rush Green Motors - Battery storage
RNA Energy limited · 24/00314/FP
50Application Withdrawn2025-03-25
Tophams Solar Farm
Pathfinder Clean Energy UK Dev Limited · 22/00741/FP · 26.4 mo to decide
8Awaiting Construction2024-06-17
Letchworth Garden City - Urban Reserve Energy Storage Facility
AMP Energy Services Limited · 24/00226/FP · 2 mo to decide
5Awaiting Construction2024-04-10
St Ippolyts - Solar Farm & Battery Storage
RNA Energy Limited · 22/00709/FP · 20.3 mo to decide
12.5Revised2023-11-22
Wymondley Solar Farm, Great Wymondley
AGR Power Limited · 21/03380/FP
Awaiting Construction2021-12-14
Rush Green Motors - Battery storage
RNA Energy limited · 21/01860/FP · 3.7 mo to decide
50Revised2021-10-06
Letchworth Power Energy Storage Facility
AMP Energy Services Limited · 20/02603/FP
5Revised2020-11-18

Does North Hertfordshire approve battery storage schemes?

Yes — of the 6 battery storage schemes North Hertfordshire has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in North Hertfordshire?

The median time from application to decision is 20.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has North Hertfordshire consented?

26 MW has been consented across 6 approved schemes. A further 5 applications awaits a decision.

Other technologies in North Hertfordshire

Solar in North HertfordshireOnshore wind in North Hertfordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com