Renewable planning › Battery storage › South Gloucestershire
Battery storage planning in South Gloucestershire
South Gloucestershire has decided 15 battery storage schemes and approved 93% of them, taking a median of 8.3 months to decide. Consented capacity: 898 MW. 5 applications still awaiting a decision.
How South Gloucestershire compares
Against the 137 UK authorities with 5+ battery storage decisions, South Gloucestershire sits in the 40th percentile for approval rate (1 points above the England average) and the 24th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (20)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Central Park - Solar Farm & Battery Storage Severnside Distribution Lane Limited · P26/00067/F | — | Application Submitted | 2026-01-13 |
Quarry Road, Alveston - Micro Battery Energy Storage System AMP Clean Energy · P25/02752/F | 0.2 | Application Submitted | 2026-01-05 |
Stoke Gifford Bypass, Curtis Lane - Micro Energy Storage System AMP Clean Energy · P25/02853/F | 0.2 | Application Submitted | 2025-12-18 |
Earthcott Green Farm, Earthcott Green - Battery Energy Storage Immersa Limited · P23/01244/F · 28 mo to decide | 200 | Awaiting Construction | 2025-07-30 |
Hill Court Solar farm & Battery storage Longlands Solar Farm Limited · P25/00579/F · 2.6 mo to decide | 35 | Awaiting Construction | 2025-05-29 |
Cattybrook Solar Farm Luminous Energy Limited · P23/03430/F · 16.1 mo to decide | — | Awaiting Construction | 2025-04-17 |
Severn Road, Hallen - Battery Storage Facility EL Avonmouth Limited · P23/02741/F · 17 mo to decide | 70 | Awaiting Construction | 2025-02-24 |
Mousewell Farm, Besom Lane - Solar Farm RWE Renewables UK Limited · P24/03001/F | — | Application Submitted | 2024-12-30 |
Iron Acton Substation, Latteridge Lane - Battery Energy Storage System Balance Power Projects Limited · P23/02405/F · 11.9 mo to decide | 99 | Awaiting Construction | 2024-08-16 |
Westerleigh Hill, Westerleigh - Battery Energy Storage Facility Immersa Limited · P23/01180/F · 15.7 mo to decide | 200 | Awaiting Construction | 2024-07-19 |
Larks Lane & Latteridge Lane, Latteridge - Battery Storage Facility Anglo Renewables · P23/02270/F · 4.9 mo to decide | 49.9 | Awaiting Construction | 2024-01-04 |
Larks Lane, Iron Acton - Battery Storage Facility HD000ACT Limited · P23/01616/F | 20 | Application Submitted | 2023-05-31 |
Lower Larks Farm - Battery storage IPP Cero Generation · P22/03743/F · 8.8 mo to decide | 99.9 | Awaiting Construction | 2023-04-14 |
Says Court Farm, Coalpit Heath - Battery Energy Storage Anglo Renewables Limited · P22/03920/F · 3.4 mo to decide | 50 | Awaiting Construction | 2022-11-02 |
Patch Elm Lane - Battery Storage Green Frog Ventures Limited · P21/07489/F · 3.9 mo to decide | 35 | Awaiting Construction | 2022-03-18 |
Elm Farm solar farm and Battery storage Enso Energy Limited · P21/04721/F · 6.8 mo to decide | — | Application Refused | 2022-01-28 |
The Wave - Solar & Battery Development The Wave Group Limited · P21/00356/F · 8.3 mo to decide | — | Awaiting Construction | 2021-10-22 |
Larks Lane, Iron Acton - Battery Storage Facility RE Projects Development · P21/03995/F · 1.6 mo to decide | — | Awaiting Construction | 2021-07-16 |
Larks Green Solar Farm Enso Energy / Iron Acton Green · P20/13909/F · 4.5 mo to decide | 49.5 | Operational | 2021-01-05 |
Old Green Farm, Alveston Battery Storage Ecotricity · PT17/1992/RVC · 30.7 mo to decide | 10 | Awaiting Construction | 2019-11-17 |
Does South Gloucestershire approve battery storage schemes?
Yes — of the 15 battery storage schemes South Gloucestershire has decided, 93% were approved (14 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in South Gloucestershire?
The median time from application to decision is 8.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has South Gloucestershire consented?
898 MW has been consented across 14 approved schemes. A further 5 applications awaits a decision.
Other technologies in South Gloucestershire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.