Battery storage planning in East Riding of Yorkshire

East Riding of Yorkshire has decided 19 battery storage schemes and approved 95% of them, taking a median of 5.3 months to decide. Consented capacity: 1,458 MW. 2 applications still awaiting a decision.

95%
Approved
18 granted · 1 refused
5.3 mo
Median decision
UK 6 mo
1,458 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How East Riding of Yorkshire compares

Against the 137 UK authorities with 5+ battery storage decisions, East Riding of Yorkshire sits in the 43rd percentile for approval rate (3 points above the England average) and the 57th percentile for speed.

Decisions by year

510Approved — 1 (2017)117Approved — 2 (2018)Refused — 1 (2018)318Approved — 2 (2020)220Approved — 2 (2022)222Approved — 1 (2023)123Approved — 3 (2024)324Approved — 7 (2025)725
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Ryedale Farm, Seaton Common Lane - Battery Energy Storage
RPC Elmya Carnation Foxdale Limited · 25/01321/STPLF · 5.6 mo to decide
300Awaiting Construction2025-12-12
Bridlington And District Hospital, Bessingby Road - Battery Unit
York Teaching Hospital NHS Foundation Trust · 25/02569/PLF · 1.8 mo to decide
0.43Awaiting Construction2025-11-12
Tara Melbourne Road, Thornton - Battery Energy Storage Facility
Rewe 9 Limited · 25/00852/STPLF · 4.5 mo to decide
200Awaiting Construction2025-08-28
Humberfield Recycling Centre - Battery Energy Storage Facility
FCC Environment · 25/01104/PLF · 2.5 mo to decide
30Awaiting Construction2025-07-28
Staithes Road, Saltend -Battery Energy Storage System
SFEL One Limited · 24/03387/STPLF · 7.1 mo to decide
240Awaiting Construction2025-07-21
Kingston International Business Park - Battery Energy Storage System
Story Contracting Limited · 24/02654/STPLF · 8.7 mo to decide
200Awaiting Construction2025-07-02
Thornton Battery Storage
Greenfield Energy Developments Limited · 25/01685/STPLF
400Application Submitted2025-06-26
Newton Farm, Tongue Lane - Solar Farm & Battery Storage
Newstead Farm · 24/02946/PLF · 5.7 mo to decide
Awaiting Construction2025-06-11
Froghall Farm, Wyton Road - Solar Farm & Battery Energy Storage
GAM Capital Limited · 23/00760/STPLFE · 19.5 mo to decide
20Awaiting Construction2024-11-11
Creyke Beck Substation - Battery Storage
Albanwise Synergy Limited · 23/03926/STPLF · 3.1 mo to decide
Awaiting Construction2024-03-25
Old Chalk Pit, West Back Side - Three Oaks Renewable Park
Ridge Clean Energy Limited · 22/02777/STPLF · 16.9 mo to decide
Awaiting Construction2024-03-21
Croxby Hall Farm, Inglemire Lane - Solar Farm & Battery Storage
UOH Energy Co Limited · 23/02045/STPLF
Application Withdrawn2024-03-05
Snuff Mill Lane Gates - Solar Farm & Battery Storage
UOH Energy Co Limited · 23/02046/STPLF
Application Withdrawn2024-03-05
Pillswood Phase 2
Harmony Energy Storage · 19/01449/STPLF · 50.1 mo to decide
49.5Operational2023-07-25
Soay Solar Farm and Greener Grid Park
Statkraft Uk Limited · 21/04505/STPLF · 10.1 mo to decide
200Under Construction2022-11-28
Field House Solar Farm
Albanwise Synergy Limited · 22/00824/STPLF · 3.5 mo to decide
40Awaiting Construction2022-07-08
Creyke Beck Substation - Solar Farm & Battery Storage
Albanwise Synergy Limited · 21/02335/STPLF · 5.1 mo to decide
Revised2022-01-06
Back Lane, Skerne - Solar Farm & Battery Storage
BayWa r.e. UK Limited · 20/01962/STPLF · 3.4 mo to decide
30Awaiting Construction2020-10-23
Scurf Dyke - Solar Farm
BayWa r.e. UK Limited · 19/04321/STPLF · 2.1 mo to decide
Awaiting Construction2020-03-18
Pillswood Phase 1
Harmony Energy Storage · 17/01993/STPLF · 18.8 mo to decide
49.5Operational2018-10-30
Ferndale Park Newfields Industrial Estate
Century Power · 17/03684/PLF · 8.7 mo to decide
Application Refused2018-07-20
Salt End Lane
AMPY Energy Services · 17/03771/STPLF · 3.6 mo to decide
49Planning Permission Expired2018-02-28
Creyke Beck
Statera Energy · 17/01372/STPLF · 2.3 mo to decide
49.9Operational2017-06-30

Does East Riding of Yorkshire approve battery storage schemes?

Yes — of the 19 battery storage schemes East Riding of Yorkshire has decided, 95% were approved (18 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in East Riding of Yorkshire?

The median time from application to decision is 5.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has East Riding of Yorkshire consented?

1,458 MW has been consented across 18 approved schemes. A further 2 applications awaits a decision.

Other technologies in East Riding of Yorkshire

Solar in East Riding of YorkshireOnshore wind in East Riding of Yorkshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.