Renewable planning › Battery storage › East Riding of Yorkshire
Battery storage planning in East Riding of Yorkshire
East Riding of Yorkshire has decided 19 battery storage schemes and approved 95% of them, taking a median of 5.3 months to decide. Consented capacity: 1,458 MW. 2 applications still awaiting a decision.
How East Riding of Yorkshire compares
Against the 137 UK authorities with 5+ battery storage decisions, East Riding of Yorkshire sits in the 43rd percentile for approval rate (3 points above the England average) and the 57th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (23)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Ryedale Farm, Seaton Common Lane - Battery Energy Storage RPC Elmya Carnation Foxdale Limited · 25/01321/STPLF · 5.6 mo to decide | 300 | Awaiting Construction | 2025-12-12 |
Bridlington And District Hospital, Bessingby Road - Battery Unit York Teaching Hospital NHS Foundation Trust · 25/02569/PLF · 1.8 mo to decide | 0.43 | Awaiting Construction | 2025-11-12 |
Tara Melbourne Road, Thornton - Battery Energy Storage Facility Rewe 9 Limited · 25/00852/STPLF · 4.5 mo to decide | 200 | Awaiting Construction | 2025-08-28 |
Humberfield Recycling Centre - Battery Energy Storage Facility FCC Environment · 25/01104/PLF · 2.5 mo to decide | 30 | Awaiting Construction | 2025-07-28 |
Staithes Road, Saltend -Battery Energy Storage System SFEL One Limited · 24/03387/STPLF · 7.1 mo to decide | 240 | Awaiting Construction | 2025-07-21 |
Kingston International Business Park - Battery Energy Storage System Story Contracting Limited · 24/02654/STPLF · 8.7 mo to decide | 200 | Awaiting Construction | 2025-07-02 |
Thornton Battery Storage Greenfield Energy Developments Limited · 25/01685/STPLF | 400 | Application Submitted | 2025-06-26 |
Newton Farm, Tongue Lane - Solar Farm & Battery Storage Newstead Farm · 24/02946/PLF · 5.7 mo to decide | — | Awaiting Construction | 2025-06-11 |
Froghall Farm, Wyton Road - Solar Farm & Battery Energy Storage GAM Capital Limited · 23/00760/STPLFE · 19.5 mo to decide | 20 | Awaiting Construction | 2024-11-11 |
Creyke Beck Substation - Battery Storage Albanwise Synergy Limited · 23/03926/STPLF · 3.1 mo to decide | — | Awaiting Construction | 2024-03-25 |
Old Chalk Pit, West Back Side - Three Oaks Renewable Park Ridge Clean Energy Limited · 22/02777/STPLF · 16.9 mo to decide | — | Awaiting Construction | 2024-03-21 |
Croxby Hall Farm, Inglemire Lane - Solar Farm & Battery Storage UOH Energy Co Limited · 23/02045/STPLF | — | Application Withdrawn | 2024-03-05 |
Snuff Mill Lane Gates - Solar Farm & Battery Storage UOH Energy Co Limited · 23/02046/STPLF | — | Application Withdrawn | 2024-03-05 |
Pillswood Phase 2 Harmony Energy Storage · 19/01449/STPLF · 50.1 mo to decide | 49.5 | Operational | 2023-07-25 |
Soay Solar Farm and Greener Grid Park Statkraft Uk Limited · 21/04505/STPLF · 10.1 mo to decide | 200 | Under Construction | 2022-11-28 |
Field House Solar Farm Albanwise Synergy Limited · 22/00824/STPLF · 3.5 mo to decide | 40 | Awaiting Construction | 2022-07-08 |
Creyke Beck Substation - Solar Farm & Battery Storage Albanwise Synergy Limited · 21/02335/STPLF · 5.1 mo to decide | — | Revised | 2022-01-06 |
Back Lane, Skerne - Solar Farm & Battery Storage BayWa r.e. UK Limited · 20/01962/STPLF · 3.4 mo to decide | 30 | Awaiting Construction | 2020-10-23 |
Scurf Dyke - Solar Farm BayWa r.e. UK Limited · 19/04321/STPLF · 2.1 mo to decide | — | Awaiting Construction | 2020-03-18 |
Pillswood Phase 1 Harmony Energy Storage · 17/01993/STPLF · 18.8 mo to decide | 49.5 | Operational | 2018-10-30 |
Ferndale Park Newfields Industrial Estate Century Power · 17/03684/PLF · 8.7 mo to decide | — | Application Refused | 2018-07-20 |
Salt End Lane AMPY Energy Services · 17/03771/STPLF · 3.6 mo to decide | 49 | Planning Permission Expired | 2018-02-28 |
Creyke Beck Statera Energy · 17/01372/STPLF · 2.3 mo to decide | 49.9 | Operational | 2017-06-30 |
Does East Riding of Yorkshire approve battery storage schemes?
Yes — of the 19 battery storage schemes East Riding of Yorkshire has decided, 95% were approved (18 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in East Riding of Yorkshire?
The median time from application to decision is 5.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has East Riding of Yorkshire consented?
1,458 MW has been consented across 18 approved schemes. A further 2 applications awaits a decision.
Other technologies in East Riding of Yorkshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.