Battery storage planning in Newport

Newport has decided 6 battery storage schemes and approved 100% of them, taking a median of 3 months to decide. Consented capacity: 392 MW.

100%
Approved
6 granted · 0 refused
3 mo
Median decision
UK 6 mo
392 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Newport compares

Against the 137 UK authorities with 5+ battery storage decisions, Newport sits in the 73rd percentile for approval rate (8 points above the England average) and the 88th percentile for speed.

Decisions by year

35Approved — 1 (2016)116Approved — 1 (2022)122Approved — 1 (2024)124Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (6)

SchemeMWStatusDecided
Docks Way Disposal Site, Docks Way - Battery Energy Storage System
Newport City Council · 25/0991 · 2.8 mo to decide
1Awaiting Construction2026-02-12
Uskmouth Power Station, West Nash Road - Battery Energy Storage
Simec Uskmouth Power Limited · 25/0407 · 4.3 mo to decide
Awaiting Construction2025-10-08
Leeway House, Leeway Industrial Estate - Battery Energy Storage System
Aldustria Limited · 25/0084 · 5.1 mo to decide
20.6Awaiting Construction2025-07-25
Uskmouth Power Station, West Nash Road - Battery Storage Facility
AW1 Energy Storage Limited · 23/0949 · 2.6 mo to decide
120Under Construction2024-01-11
Uskmouth Power Station - Battery Storage
Simec Atlantic Energy Uskmouth Power Station · 22/0823 · 3.2 mo to decide
230Under Construction2022-12-07
Traston Road
Field Energy · 16/0855 · 2.5 mo to decide
20Operational2016-11-03

Does Newport approve battery storage schemes?

Yes — of the 6 battery storage schemes Newport has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Newport?

The median time from application to decision is 3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Newport consented?

392 MW has been consented across 6 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Newport

Solar in NewportOnshore wind in Newport

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.