Battery storage planning in Swindon

Swindon has decided 6 battery storage schemes and approved 100% of them, taking a median of 6.2 months to decide. Consented capacity: 152 MW. 1 application still awaiting a decision.

100%
Approved
6 granted · 0 refused
6.2 mo
Median decision
UK 6 mo
152 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Swindon compares

Against the 137 UK authorities with 5+ battery storage decisions, Swindon sits in the 73rd percentile for approval rate (8 points above the England average) and the 43rd percentile for speed.

Decisions by year

35Approved — 2 (2018)218Approved — 2 (2020)220Approved — 1 (2023)123Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Queenslaine Farm, Highworth Road - Battery Energy Storage System
Elgin Energy · S/25/0250 · 6.2 mo to decide
66Awaiting Construction2025-09-12
Catsbrain Farm - Battery Storage
Conrad Energy (Developments) II Limited · S/22/1051 · 14.8 mo to decide
30Awaiting Construction2023-10-03
Brindley Close (Extension)
Public Power Solutions · S/20/0850 · 1.7 mo to decide
6Under Construction2020-09-04
Corner Copse Solar Farm
BayWa r.e. UK Limited · S/19/1097 · 10.8 mo to decide
Under Construction2020-06-25
Mannington Battery Storage Plant
Still Waters Green Technology · S/17/1879 · 12.5 mo to decide
49.9Operational2018-12-07
B and Q Distribution Centre Highworth Road
Kingfisher / Solar Century · S/18/0856 · 1.7 mo to decide
Operational2018-08-21
Catsbrain Farm
Green Hedge · S/17/0979 · 4.5 mo to decide
30Revised2017-11-03

Does Swindon approve battery storage schemes?

Yes — of the 6 battery storage schemes Swindon has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Swindon?

The median time from application to decision is 6.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Swindon consented?

152 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.

Other technologies in Swindon

Solar in SwindonOnshore wind in Swindon

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.