Renewable planning › Battery storage › Swindon
Battery storage planning in Swindon
Swindon has decided 6 battery storage schemes and approved 100% of them, taking a median of 6.2 months to decide. Consented capacity: 152 MW. 1 application still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Swindon compares
Against the 137 UK authorities with 5+ battery storage decisions, Swindon sits in the 73rd percentile for approval rate (8 points above the England average) and the 43rd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Queenslaine Farm, Highworth Road - Battery Energy Storage System Elgin Energy · S/25/0250 · 6.2 mo to decide | 66 | Awaiting Construction | 2025-09-12 |
Catsbrain Farm - Battery Storage Conrad Energy (Developments) II Limited · S/22/1051 · 14.8 mo to decide | 30 | Awaiting Construction | 2023-10-03 |
Brindley Close (Extension) Public Power Solutions · S/20/0850 · 1.7 mo to decide | 6 | Under Construction | 2020-09-04 |
Corner Copse Solar Farm BayWa r.e. UK Limited · S/19/1097 · 10.8 mo to decide | — | Under Construction | 2020-06-25 |
Mannington Battery Storage Plant Still Waters Green Technology · S/17/1879 · 12.5 mo to decide | 49.9 | Operational | 2018-12-07 |
B and Q Distribution Centre Highworth Road Kingfisher / Solar Century · S/18/0856 · 1.7 mo to decide | — | Operational | 2018-08-21 |
Catsbrain Farm Green Hedge · S/17/0979 · 4.5 mo to decide | 30 | Revised | 2017-11-03 |
Does Swindon approve battery storage schemes?
Yes — of the 6 battery storage schemes Swindon has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Swindon?
The median time from application to decision is 6.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Swindon consented?
152 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.
Other technologies in Swindon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.