Renewable planning › Battery storage › Swansea
Battery storage planning in Swansea
Swansea has decided 9 battery storage schemes and approved 89% of them, taking a median of 3.1 months to decide. Consented capacity: 321 MW. 6 applications still awaiting a decision.
How Swansea compares
Against the 137 UK authorities with 5+ battery storage decisions, Swansea sits in the 33rd percentile for approval rate (3 points below the England average) and the 85th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (15)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Heol Y Mynydd Road - Micro Energy Storage AMP Clean Energy · 2026/0198/FUL | 0.2 | Application Submitted | 2026-02-06 |
Morfa Stadium, Normandy Road - Battery Storage AMP Clean Energy · 2026/0191/FUL | 0.2 | Application Submitted | 2026-02-05 |
Rhydypandy Road, Morriston - Battery Energy Storage System Statkraft UK · 2025/0855/FUL · 7.9 mo to decide | 100 | Awaiting Construction | 2025-12-18 |
Abergelli Farm, Felindre - Battery Storage EDF Energy Renewables · 2025/1580/FUL | 250 | Application Submitted | 2025-07-22 |
Ferryboat Close, Swansea Enterprise Park - Micro Energy Storage Unit AMP Clean Energy · 2025/1264/FUL · 1.7 mo to decide | 0.2 | Awaiting Construction | 2025-07-22 |
Swansea Enterprise Park, Clarion Close - Energy Storage Facility AMP Clean Energy · 2025/0729/FUL · 2.8 mo to decide | 0.2 | Application Refused | 2025-06-27 |
Garngoch Industrial Estate, Penllergaer - Micro Energy Storage Facility AMP Clean Energy · 2025/0965/FUL · 1.7 mo to decide | 0.2 | Awaiting Construction | 2025-06-27 |
Gwenlais Farm, Carmel Road - Gwenlais Solar Farm Solar Securities Group Limited · DNS CAS-02282-Z9M8L7 · 30.8 mo to decide | — | Awaiting Construction | 2025-06-11 |
Kemys Way, Swansea Enterprise Park - Battery Energy Storage AMP Clean Energy · 2025/0956/FUL | 0.2 | Application Submitted | 2025-05-01 |
Kemys Way - Micro Energy Storage Facility AMP Clean Energy · 2025/0957/FUL | 0.2 | Application Submitted | 2025-05-01 |
Lletty Scilp Farm, Swansea North - Energy Storage System Innova Renewables · 2024/2401/FUL | 400 | Application Submitted | 2025-03-07 |
Bryntywod, Llangyfelach - Battery Energy Storage System FRV TH Powertek Limited · 2024/1634/FUL · 5.1 mo to decide | 200 | Awaiting Construction | 2025-02-06 |
Brynwhilach Solar Farm, Morriston - Battery Storage Swansea Bay University Health Board · 2022/2922/FUL · 2.7 mo to decide | 1 | Awaiting Construction | 2023-03-29 |
John Green Frog Power Compound, John North Road - Battery System Green Frog Power Limited · 2022/2356/FUL · 3.1 mo to decide | 20 | Awaiting Construction | 2023-01-20 |
Swansea Greener Grid Park Statkraft UK / Swansea Grid Solutions · 2021/0163/FUL · 6.6 mo to decide | — | Under Construction | 2021-08-09 |
Does Swansea approve battery storage schemes?
Yes — of the 9 battery storage schemes Swansea has decided, 89% were approved (8 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Swansea?
The median time from application to decision is 3.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Swansea consented?
321 MW has been consented across 8 approved schemes. A further 6 applications awaits a decision.
Other technologies in Swansea
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.