Renewable planning › Battery storage › Basildon
Battery storage planning in Basildon
Basildon has decided 6 battery storage schemes and approved 83% of them, taking a median of 7.9 months to decide. Consented capacity: 115 MW. 6 applications still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Basildon compares
Against the 137 UK authorities with 5+ battery storage decisions, Basildon sits in the 17th percentile for approval rate (9 points below the England average) and the 26th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (14)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Miles Gray Road, Steeple View - Micro Energy Storage AMP Clean Energy · 26/00065/FULL | 0.2 | Application Submitted | 2026-01-26 |
Burnt Mills Industrial Estate, Hovefields Avenue - Battery Energy Storage AMP Clean Energy · 25/01630/FULL | 0.2 | Application Submitted | 2025-12-15 |
Ambrose Close & Gloucester Park, Broadmayne - Energy Storage System AMP Clean Energy · 25/00164/FULL | 0.2 | Application Withdrawn | 2025-11-04 |
Whitmore Way - Micro Energy Storage Project AMP Clean Energy · 25/00166/FULL | 0.2 | Application Withdrawn | 2025-11-04 |
Rayleigh Spur Roundabout, Benfleet - Battery Energy Storage System Renewable Energy Systems RES ltd (Beaufort) · 25/00898/FULL | 150 | Application Submitted | 2025-07-02 |
Tesco Extra, Hazelmere - Battery Energy Storage Tesco Plc · 25/00027/FULL · 2.3 mo to decide | 0.25 | Awaiting Construction | 2025-04-10 |
Lower Dunton Road - Battery Energy Storage System LJ Construction UK Limited · 24/01239/FULL | 368 | Application Submitted | 2024-10-25 |
Barleylands Solar Farm Enso Energy Limited · 23/01468/FULL · 10.3 mo to decide | — | Awaiting Construction | 2024-10-08 |
Southend Arterial Road - Battery Energy Storage Enso Green Holdings Limited · 24/00142/FULL | — | Application Submitted | 2024-02-09 |
Whites Farm - Battery Storage Anglo Renewables Limited · 22/01108/FULL · 11.2 mo to decide | 49.9 | Application Refused | 2023-07-06 |
Nevendon Battery Storage Extension Belectric Solar Limited · 23/00079/FULL · 3.6 mo to decide | 5 | Operational | 2023-05-15 |
Barleylands Solar Farm Enso Energy Limited · 22/00411/FULL · 11.6 mo to decide | — | Revised | 2023-03-23 |
Dollymans Storage Statera Energy / Dollymans Storage · 21/00522/FUL · 5.4 mo to decide | 99.98 | Operational | 2021-11-05 |
Nevendon Belectric UK / Foresight | 10 | Operational | — |
Does Basildon approve battery storage schemes?
Yes — of the 6 battery storage schemes Basildon has decided, 83% were approved (5 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Basildon?
The median time from application to decision is 7.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Basildon consented?
115 MW has been consented across 5 approved schemes, with 50 MW refused. A further 6 applications awaits a decision.
Other technologies in Basildon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.