Battery storage planning in Herefordshire, County of

Herefordshire, County of has decided 6 battery storage schemes and approved 100% of them, taking a median of 3.8 months to decide. Consented capacity: 40 MW. 2 applications still awaiting a decision.

100%
Approved
6 granted · 0 refused
3.8 mo
Median decision
UK 6 mo
40 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Herefordshire, County of compares

Against the 137 UK authorities with 5+ battery storage decisions, Herefordshire, County of sits in the 73rd percentile for approval rate (8 points above the England average) and the 76th percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 1 (2022)122Approved — 1 (2023)123Approved — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (8)

SchemeMWStatusDecided
Chapel Road - Micro Energy Storage Facility
AMP Clean Energy · P250364/F · 1.9 mo to decide
0.2Awaiting Construction2025-03-27
Green Spider Climbing, Ramsden Road - Micro Energy Storage Facility
Aggregated Micro Power Holdings Plc · P241158/F · 2.1 mo to decide
0.2Awaiting Construction2024-07-16
The Hop Pocket - Battery Storage Facility
The Hop Pocket Shopping Village · P232448/F · 3.8 mo to decide
Awaiting Construction2023-12-05
Peterstow Gas Compressor Station, Hentland - Energy Storage System
Novus Renewable Services Limited · P231390/F
49.9Application Submitted2023-05-02
Larport, Clay Hill Pit - Solar Photovoltaics & Battery storage
Conrad Energy · P213963/F · 7 mo to decide
Operational2022-05-27
Perserverance Road
Noriker Power · P200967/F · 7.7 mo to decide
20Awaiting Construction2020-11-13
Perseverance Road
Noriker Power · P181659/F
20Revised2018-05-04
Land to the west of Clay Hill Pit / Larport Farm
Anesco (formerly owned by Energy Reservoirs) · P162400/F
20Operational2016-08-23

Does Herefordshire, County of approve battery storage schemes?

Yes — of the 6 battery storage schemes Herefordshire, County of has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Herefordshire, County of?

The median time from application to decision is 3.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Herefordshire, County of consented?

40 MW has been consented across 6 approved schemes. A further 2 applications awaits a decision.

Other technologies in Herefordshire, County of

Solar in Herefordshire, County ofOnshore wind in Herefordshire, County of

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.