Renewable planning › Battery storage › Torridge
Battery storage planning in Torridge
Torridge has decided 5 battery storage schemes and approved 100% of them, taking a median of 7.1 months to decide. Consented capacity: 175 MW. 4 applications still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Torridge compares
Against the 137 UK authorities with 5+ battery storage decisions, Torridge sits in the 73rd percentile for approval rate (8 points above the England average) and the 33rd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (11)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Golf Links Road, Northam - Micro Energy Storage AMP Clean Energy · 1/0122/2026/FUL | 0.2 | Application Submitted | 2026-02-12 |
West Webbery Farm, The Water - Battery Energy Storage Enray SPV 241491 Limited · 1/0939/2025/FULM | 99.4 | Application Submitted | 2025-12-18 |
Bulworthy Farm, Stoney Cross - Solar Photovoltaic Array Noventum Power Limited · 1/0470/2025/FULM | 49.99 | Application Submitted | 2025-07-30 |
Gammaton Barton Farm, Alverdiscott - Battery Energy Storage Torridge District Council · 1/0268/2025/FULM · 3.7 mo to decide | 100 | Awaiting Construction | 2025-07-17 |
Stoneworthy - Battery Energy Storage System RES Limited · 1/0514/2024/FULM · 13 mo to decide | 49.9 | Awaiting Construction | 2025-07-03 |
Ford Rise - Micro Energy Storage AMP Energy Services Limited · 1/0084/2025/FUL | 0.2 | Application Withdrawn | 2025-03-26 |
Torridge Pool, Benson Drive - Micro Energy Storage Facility AMP Energy Services Limited · 1/0085/2025/FUL | 0.2 | Application Withdrawn | 2025-03-26 |
Pinkworthy Farm, Pyworthy - Battery Storage Private Developer · 1/0127/2024/FUL · 6 mo to decide | 25 | Awaiting Construction | 2024-09-05 |
Pinkworthy Farm, Pyworthy - Battery Storage Private Developer · 1/0146/2023/OUT · 16.9 mo to decide | 50 | Revised | 2024-08-09 |
Deptford Farm, Ebberley Hill - Battery Storage Elgin Energy ES Co Limited · 1/1225/2023/FULM · 7.2 mo to decide | — | Awaiting Construction | 2024-07-26 |
East Rightadown Farm, Brandis Corner - Battery Storage Black Torrington Solar Limited · 1/1300/2022/FULM · 7 mo to decide | — | Awaiting Construction | 2023-09-01 |
Does Torridge approve battery storage schemes?
Yes — of the 5 battery storage schemes Torridge has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Torridge?
The median time from application to decision is 7.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Torridge consented?
175 MW has been consented across 5 approved schemes. A further 4 applications awaits a decision.
Other technologies in Torridge
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.