Battery storage planning in Solihull

Solihull has decided 8 battery storage schemes and approved 88% of them, taking a median of 12.6 months to decide. Consented capacity: 535 MW. 7 applications still awaiting a decision.

88%
Approved
7 granted · 1 refused
12.6 mo
Median decision
UK 6 mo
535 MW
Consented
15 MW refused
3
Appeals
3 allowed on appeal

How Solihull compares

Against the 137 UK authorities with 5+ battery storage decisions, Solihull sits in the 29th percentile for approval rate (4 points below the England average) and the 7th percentile for speed.

Decisions by year

35Approved — 2 (2023)223Refused — 1 (2024)124Approved — 5 (2025)525
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (15)

SchemeMWStatusDecided
Henwood Lane, Catherine De Barnes - Battery Storage Facility
ARL016 · PL/2023/01954/PPFL · 22.4 mo to decide
98Awaiting Construction2025-07-30
Burton Green Farm - Battery Energy Storage
Conrad Energy (Developments) Limited · PL/2024/01948/PPFL · 9.4 mo to decide
100Awaiting Construction2025-07-09
Tanners Lane - Battery Energy Storage System
Tag Energy Development UK Limited · PL/2024/02694/PPFL · 7.5 mo to decide
30Awaiting Construction2025-06-23
Benton Green Lane - Battery Energy Storage System
Tamara Ettenfield · PL/2025/01145/PPFL
70Application Submitted2025-06-06
Hill House Farm, Coventry Road - Battery Energy Storage System
Root Power South Limited · PL/2025/00806/PPFL
20Application Submitted2025-04-14
Hodgetts Lane, Berkswell - Electricity Storage Facility
Coventry Energy Storage Limited · PL/2023/02196/PPFL · 15 mo to decide
49.9Awaiting Construction2025-01-25
Beechwood Farm, Hodgetts Lane - Battery Storage
Enso Energy Limited · PL/2023/00839/PPFL · 20.8 mo to decide
57Awaiting Construction2025-01-09
Beechwood Farm, Hodgetts Lane - Battery Storage
Enso Energy Limited · PL/2024/01392/PPFL
57Application Submitted2024-07-19
Hodgetts Lane, Berkswell - Electricity Storage Facility
Coventry Energy Storage Limited · PL/2024/01261/PPFL
49.9Application Submitted2024-07-02
Ryton End, Barston - Battery Storage
Greenfield Energy Consultancy Limited · PL/2022/02068/PPFL · 19.2 mo to decide
15Application Refused2024-05-02
Tanners Lane - Battery Energy Storage System
Tag Energy Development UK Limited · PL/2023/02051/PPFL
30Revised2024-03-05
Little Beanit Farm, Balsall Common - Battery Storage
Penso Power (BW ESS) · PL/2022/02308/PPFL · 10.1 mo to decide
200Under Construction2023-08-31
Hodgetts Lane, Berkswell - Electricity Storage Facility
Anglo ES Berkswell Limited · PL/2023/01595/PPFL
49.9Application Submitted2023-07-28
Jaguar Land Rover, Lode Lane � Battery Storage Unit
Jaguar Landrover Limited · PL/2023/00838/PPFL · 2.6 mo to decide
Awaiting Construction2023-07-06
Hodgetts Lane, Berkswell - Electricity Storage Facility
Coventry Energy Storage Limited · PL/2022/02581/PPFL
49.9Revised2022-12-08

Does Solihull approve battery storage schemes?

Yes — of the 8 battery storage schemes Solihull has decided, 88% were approved (7 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Solihull?

The median time from application to decision is 12.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Solihull consented?

535 MW has been consented across 7 approved schemes, with 15 MW refused. A further 7 applications awaits a decision.

Other technologies in Solihull

Solar in SolihullOnshore wind in Solihull

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.