Renewable planning › Battery storage › Bolsover
Battery storage planning in Bolsover
Bolsover has decided 6 battery storage schemes and approved 100% of them, taking a median of 1.9 months to decide. Consented capacity: 151 MW. 1 application still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Bolsover compares
Against the 137 UK authorities with 5+ battery storage decisions, Bolsover sits in the 73rd percentile for approval rate (8 points above the England average) and the 95th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (8)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wharf Road & Beaufit Lane, Pinxton - Micro Energy Storage AMP Clean Energy · 25/00488/FUL · 1.6 mo to decide | 0.2 | Awaiting Construction | 2026-01-15 |
Hurst Farm, Mansfield Road - Battery Energy Storage System Lightsource BP · 25/00302/FUL · 4.7 mo to decide | 99.9 | Awaiting Construction | 2025-12-19 |
Creswell Road, Clowne - Battery Storage AMP Clean Energy · 25/00023/FUL · 1.7 mo to decide | 0.2 | Awaiting Construction | 2025-03-10 |
Plymouth Avenue, Pinxton - Battery Energy Storage Facility AMP Energy Services Limited · 24/00153/FUL · 1.7 mo to decide | 0.2 | Awaiting Construction | 2024-05-24 |
High View Road, South Normanton - Battery Energy Storage Unit Mercia Power Response Limited · 24/00116/FUL | — | Application Withdrawn | 2024-05-09 |
Creswell Road, Clowne - Battery Storage AMP Clean Energy · 23/00182/FUL · 2.1 mo to decide | 0.2 | Revised | 2023-06-07 |
Newton Wood Farm Anesco · 20/00202/FUL · 5.1 mo to decide | 49.9 | Awaiting Construction | 2020-10-28 |
Oxcroft Solar Farm Anesco · 16/00145/FUL | 1 | Operational | 2016-03-30 |
Does Bolsover approve battery storage schemes?
Yes — of the 6 battery storage schemes Bolsover has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Bolsover?
The median time from application to decision is 1.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Bolsover consented?
151 MW has been consented across 6 approved schemes. A further 1 application awaits a decision.
Other technologies in Bolsover
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.