Renewable planning › Battery storage › Swale
Battery storage planning in Swale
Swale has decided 6 battery storage schemes and approved 100% of them, taking a median of 6.1 months to decide. Consented capacity: 479 MW. 2 applications still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Swale compares
Against the 137 UK authorities with 5+ battery storage decisions, Swale sits in the 73rd percentile for approval rate (8 points above the England average) and the 45th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (8)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Castle Road, Eurolink - Battery Energy Storage System AMP Clean Energy · 25/500069/FULL · 10.3 mo to decide | 0.2 | Awaiting Construction | 2025-12-22 |
Old Rides Farm, Leysdown Road - Battery Energy Storage System Nat Power · 25/503466/FULL | 1000 | Application Submitted | 2025-08-28 |
Kemsley Energy Park Battery Storage FPC Electric Land limited · 23/500771/FULL · 18.5 mo to decide | 120 | Awaiting Construction | 2024-09-30 |
Ridham Avenue, Swale Way - Kemsley Battery Energy Storage Ouse Energy Limited · 23/505752/FULL · 8 mo to decide | 249 | Awaiting Construction | 2024-09-17 |
Raspberry - Battery Storage RWE · 22/502778/EIFUL | — | Application Submitted | 2022-06-13 |
Kemsley Substation Pivot Power · 19/502514/FULL · 3.9 mo to decide | 49.9 | Operational | 2019-09-20 |
Plot 2B EurolinkV Trenport Investments · 19/502257/FULL · 2.7 mo to decide | 20 | Under Construction | 2019-07-25 |
Land off Queenborough Road UK Power Reserve · 17/503032/FULL · 4.1 mo to decide | 40 | Under Construction | 2017-10-12 |
Does Swale approve battery storage schemes?
Yes — of the 6 battery storage schemes Swale has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Swale?
The median time from application to decision is 6.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Swale consented?
479 MW has been consented across 6 approved schemes. A further 2 applications awaits a decision.
Other technologies in Swale
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.