Renewable planning › Battery storage › New Forest
Battery storage planning in New Forest
New Forest has decided 5 battery storage schemes and approved 80% of them, taking a median of 4.3 months to decide. Consented capacity: 260 MW. 1 application still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How New Forest compares
Against the 137 UK authorities with 5+ battery storage decisions, New Forest sits in the 10th percentile for approval rate (12 points below the England average) and the 71st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (6)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Bulls Copse Road, Marchwood Bypass - Battery Energy Storage System Sky UK Development Limited · 25/10640 · 7.4 mo to decide | 49.9 | Awaiting Construction | 2026-02-20 |
East Road, Marchwood - Battery Energy Storage BW ESS Development UK Limited · 25/10639 · 4.1 mo to decide | 200 | Awaiting Construction | 2025-11-13 |
Slowhill Copse, Bury Road - Battery Storage Facility Trant Engineering Limited · 24/11043 · 4.5 mo to decide | — | Awaiting Construction | 2025-04-22 |
Christchurch Road, Downton - Battery Storage GridSource Limited · 24/11099 | 0.2 | Application Submitted | 2025-01-15 |
Christchurch Road, Downton - Battery Storage GridSource Limited · 24/10748 · 1.8 mo to decide | 0.2 | Application Refused | 2024-10-17 |
Land Adj Harmer Warren Quarry New Forest Energy (formerly Somerley Estate) · 17/11630 | 10 | Under Construction | 2017-11-30 |
Does New Forest approve battery storage schemes?
Yes — of the 5 battery storage schemes New Forest has decided, 80% were approved (4 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in New Forest?
The median time from application to decision is 4.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has New Forest consented?
260 MW has been consented across 4 approved schemes. A further 1 application awaits a decision.
Other technologies in New Forest
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com