Novarly ParcelRenewable planning

Renewable planning Battery storageWest Northamptonshire

Battery storage planning in West Northamptonshire

West Northamptonshire has decided 8 battery storage schemes and approved 100% of them, taking a median of 2.6 months to decide. Consented capacity: 73 MW. 10 applications still awaiting a decision.

100%
Approved
8 granted · 0 refused
2.6 mo
Median decision
UK 6 mo
73 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

How West Northamptonshire compares

Against the 137 UK authorities with 5+ battery storage decisions, West Northamptonshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 92nd percentile for speed.

Decisions by year

35Approved — 1 (2023)123Approved — 1 (2024)124Approved — 5 (2025)525
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (20)

SchemeMWStatusDecided
Great Central Way, Byfield Road - Battery Storage
AMP Clean Energy · 2026/0517/FULL
0.2Application Submitted2026-01-29
Electricity Sub Station, Lanchester Way - Micro Energy Storage
AMP Clean Energy · 2025/3880/FULL · 2.9 mo to decide
0.2Awaiting Construction2025-11-21
Churchill Way, High March Industrial Estate - Micro Energy Storage
AMP Clean Energy · 2025/3882/FULL
0.2Application Withdrawn2025-11-12
Old Tiffield Road - Micro Energy Storage Project
AMP Clean Energy · 2025/3885/FULL · 2.6 mo to decide
0.2Awaiting Construction2025-11-10
Welton Road - Energy Storage System
AMP Clean Energy · 2025/3883/FULL · 2.6 mo to decide
0.2Awaiting Construction2025-11-10
Penvale Road - Micro Energy Battery Storage
AMP Clean Energy · 2025/3884/FULL
0.2Application Withdrawn2025-10-29
Newnham Drive, Heartlands Business Park - Micro Energy Storage Project
AMP Clean Energy · 2025/4706/FULL
0.2Application Submitted2025-10-27
New Euroline Depot, Sopwith Way - Energy Storage System
AMP Clean Energy · 2025/4704/FULL
0.2Application Submitted2025-10-27
Upper Heyford Roundabout, Daventry Link Road - Energy Storage System
AMP Clean Energy · 2025/4709/FULL
0.2Application Submitted2025-10-27
Wootton Hall Park, Mereway - Micro Energy Storage
AMP Clean Energy · 2025/4707/FULL
0.2Application Submitted2025-10-27
Northampton Road, Scarff Way - Micro Energy Storage
AMP Clean Energy · 2025/3758/FULL
0.2Application Submitted2025-10-09
Brixworth Landfill, Scaldwell Road - Solar Array & Battery Storage
SUEZ Recycling and Recovery UK Limited · 2025/4312/MAF
Application Submitted2025-10-02
Moulton Park Industrial Estate - Micro Energy Storage
AMP Clean Energy · 2025/3461/FULL · 2 mo to decide
0.2Awaiting Construction2025-10-01
Octagon Way, Weston Favell Retail Park - Energy Storage System
AMP Clean Energy · 2025/3457/FULL · 2 mo to decide
0.2Awaiting Construction2025-09-30
Newnham Grange Farm - Battery Energy Storage
Neo Environmental (Belfast) · 2025/2366/FULL
15Application Submitted2025-06-16
Welford Solar Farm - Solar Farm & Battery Storage
Welford Solar Farm Limited · 2024/0649/MAF · 10.2 mo to decide
67Awaiting Construction2024-10-11
Farm Road -Battery Energy Storage
AMP Clean Energy · 2024/3919/FULL
0.2Application Submitted2024-08-07
Halse Road - Solar Farm & Battery Storage
JBM Solar Projects Limited · WNS/2022/0557/EIA · 20.2 mo to decide
Awaiting Construction2023-11-14
Greatworth - Solar Farm & Battery Stations
JBM Solar Projects 20 Limited · WNS/2021/0935/EIA
Revised2021-12-02
Silver Spinney Farm
Thrive Renewables · S/2019/0086/FUL
5Under Construction2019-01-14

Does West Northamptonshire approve battery storage schemes?

Yes — of the 8 battery storage schemes West Northamptonshire has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in West Northamptonshire?

The median time from application to decision is 2.6 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has West Northamptonshire consented?

73 MW has been consented across 8 approved schemes. A further 10 applications awaits a decision.

Other technologies in West Northamptonshire

Solar in West NorthamptonshireOnshore wind in West Northamptonshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com