Novarly ParcelRenewable planning

Renewable planning Battery storageRochdale

Battery storage planning in Rochdale

Rochdale has decided 6 battery storage schemes and approved 83% of them, taking a median of 4.9 months to decide. Consented capacity: 147 MW. 2 applications still awaiting a decision.

83%
Approved
5 granted · 1 refused
4.9 mo
Median decision
UK 6 mo
147 MW
Consented
5 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Rochdale compares

Against the 137 UK authorities with 5+ battery storage decisions, Rochdale sits in the 17th percentile for approval rate (9 points below the England average) and the 63rd percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 1 (2021)Refused — 1 (2021)221Approved — 1 (2024)124Approved — 2 (2025)225
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Dig Gate Lane - Battery Energy Storage
Balance Power Projects Limited · 24/00043/FUL · 13.7 mo to decide
Awaiting Construction2025-04-21
Ellenroad Farm, Bentgate Street - Battery Energy Storage System
Root Power (North) Limited · 24/00917/FUL · 5.3 mo to decide
30Awaiting Construction2025-03-14
The Rake, Lower Jowkin Lane - Battery Energy Storage
Shaw-Energi Limited · 23/00816/FUL · 9.2 mo to decide
57Awaiting Construction2024-04-30
The West Side Of Hanson Street, Middleton - Battery Storage
AMP Clean Energy · 23/00104/FUL
0.2Application Submitted2023-02-10
Waterloo Farm, Furbarn Road - Battery Storage
Shaw-Energi Limited · 22/00946/FUL
57Revised2022-12-03
Astra Centre, Royal Barn Road - Energy Storage
Arlington Energy Limited · 21/01098/FUL · 2 mo to decide
40Under Construction2021-11-01
Miall Power - Energy Storage Facility
Private Developer · 21/00205/FUL · 4.6 mo to decide
5Application Refused2021-06-30
Gipsy Lane
Arlington Energy · 19/01147/FUL · 4.3 mo to decide
20Under Construction2020-03-16
Gipsy Lane Battery Energy Storage Facility
Enso Energy · 18/01106/FUL
Application Withdrawn2018-12-05

Does Rochdale approve battery storage schemes?

Yes — of the 6 battery storage schemes Rochdale has decided, 83% were approved (5 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Rochdale?

The median time from application to decision is 4.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Rochdale consented?

147 MW has been consented across 5 approved schemes, with 5 MW refused. A further 2 applications awaits a decision.

Other technologies in Rochdale

Solar in RochdaleOnshore wind in Rochdale

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com