Renewable planning › Battery storage › North East Lincolnshire
Battery storage planning in North East Lincolnshire
North East Lincolnshire has decided 8 battery storage schemes and approved 100% of them, taking a median of 9.4 months to decide. Consented capacity: 359 MW. 3 applications still awaiting a decision.
How North East Lincolnshire compares
Against the 137 UK authorities with 5+ battery storage decisions, North East Lincolnshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 15th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (12)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Gunnerby Road - 30MW Battery Energy Storage Grenergy Renewables UK Limited · DM/0513/25/FUL | 30 | Application Submitted | 2025-07-30 |
Stallingboroughe, Stallingborough Road - BESS Island Green Power · DM/0455/25/FUL | 375 | Application Submitted | 2025-06-30 |
Europa Way - Battery Storage Facility Newton Energi Limited · DM/0484/24/FUL · 5.7 mo to decide | 80 | Awaiting Construction | 2025-05-20 |
Immingham Solar Farm - Battery Storage Facility One Planet Developments Limited · DM/0108/24/FUL · 14.4 mo to decide | 30 | Awaiting Construction | 2025-05-06 |
Hewitts Avenue, New Waltham - Battery Storage Harmony HS (JB) Limited · DM/0158/24/FUL · 13.1 mo to decide | 49.9 | Awaiting Construction | 2025-03-28 |
Bradley Road - Battery Energy Storage System Renewable Connections Developments Limited · DM/1156/23/FUL · 4.9 mo to decide | 10 | Awaiting Construction | 2024-04-26 |
Trondheim Way Battery energy storage Vox Burns Limited · DM/0120/21/FUL · 23.2 mo to decide | 80 | Under Construction | 2023-01-23 |
Trondheim Way - Battery Storage Facility Vox Energy Limited · DM/1158/21/FUL · 1 mo to decide | 5 | Awaiting Construction | 2022-04-05 |
Netherlands Way - Battery Energy Facility Volta Energy Group · DM/0762/21/FUL · 4.9 mo to decide | 80 | Awaiting Construction | 2022-01-06 |
Mauxhall Farm ENGIE Renewables · DM/1145/19/FUL · 17.1 mo to decide | 24 | Planning Permission Expired | 2021-05-21 |
Kiln Lane Industrial Estate Little Fair Energy · DM/1016/17/FUL | — | Revised | 2017-11-02 |
Magnolia Street Green Hedge Energy · DM/0905/17/FUL | 20 | Abandoned | 2017-09-22 |
Does North East Lincolnshire approve battery storage schemes?
Yes — of the 8 battery storage schemes North East Lincolnshire has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in North East Lincolnshire?
The median time from application to decision is 9.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has North East Lincolnshire consented?
359 MW has been consented across 8 approved schemes. A further 3 applications awaits a decision.
Other technologies in North East Lincolnshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.