Renewable planning › Battery storage › Wrexham
Battery storage planning in Wrexham
Wrexham has decided 5 battery storage schemes and approved 100% of them, taking a median of 8.9 months to decide. Consented capacity: 16 MW. 2 applications still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Wrexham compares
Against the 137 UK authorities with 5+ battery storage decisions, Wrexham sits in the 73rd percentile for approval rate (8 points above the England average) and the 21st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wonderbank, Brymbo Road - Battery Storage Brymbo Developments Limited · P/2024/1578 · 12.5 mo to decide | — | Awaiting Construction | 2025-12-01 |
Bronwylfa Road, Rhostyllen - Energy Storage System Innova Renewables · P/2024/0155 | 400 | Application Submitted | 2024-03-08 |
National Grid Legacy Substation, Bronwylfa Road - Battery Storage Pelagic Energy · P/2023/0175 · 4.3 mo to decide | — | Awaiting Construction | 2023-07-26 |
Little Llwyn Onn - Solar Farm & Battery Storage Novus Renewable Services Limited · P/2022/0541 · 8.9 mo to decide | 16 | Awaiting Construction | 2023-03-08 |
Maelor Gasworks - Solar Farm & Battery Storage Novus Renewable Services Limited · P/2021/0676 · 15.8 mo to decide | — | Awaiting Construction | 2022-11-09 |
Bronwylfa Road, Talwrn - Battery Storage Facility Pelagic Energy · P/2021/0441 | 49.5 | Revised | 2021-05-06 |
Land SE of, Spectrum Business Park Volta Energy Storage · P/2017/0469 · 3.8 mo to decide | — | Awaiting Construction | 2017-10-05 |
Does Wrexham approve battery storage schemes?
Yes — of the 5 battery storage schemes Wrexham has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Wrexham?
The median time from application to decision is 8.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Wrexham consented?
16 MW has been consented across 5 approved schemes. A further 2 applications awaits a decision.
Other technologies in Wrexham
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com