Renewable planning › Battery storage › Blaby
Battery storage planning in Blaby
Blaby has decided 5 battery storage schemes and approved 100% of them, taking a median of 5.3 months to decide. Consented capacity: 609 MW. 2 applications still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Blaby compares
Against the 137 UK authorities with 5+ battery storage decisions, Blaby sits in the 73rd percentile for approval rate (8 points above the England average) and the 57th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Enderby Leisure Centre, Mill Lane - Energy Storage System AMP Clean Energy · 25/0030/FUL · 1.9 mo to decide | 0.2 | Awaiting Construction | 2025-03-14 |
Enderby Road Industrial Estate, Enderby Road - Battery Storage AMP Clean Energy · 25/0031/FUL | 0.2 | Application Submitted | 2025-01-22 |
Forest Road - Energy Storage System Innova Renewables · 24/0793/FUL | — | Application Submitted | 2024-09-26 |
Normanton Energy Reserve - Battery Storage Exagen SPVO2 Limited · 22/1204/FUL · 13.1 mo to decide | 500 | Awaiting Construction | 2024-01-16 |
Land at and adjacent to Leicester Forest Services Camborne Energy Storage · 17/0936/FUL · 55.7 mo to decide | 1.5 | Operational | 2022-02-07 |
National Grid Enderby Substation Gore Street · 20/0896/FUL · 5.3 mo to decide | 57 | Operational | 2021-02-04 |
Enderby Storage, Redcomb Farm Statera Energy / Gresham House · 17/1223/FUL · 2.7 mo to decide | 49.9 | Operational | 2018-01-04 |
Does Blaby approve battery storage schemes?
Yes — of the 5 battery storage schemes Blaby has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Blaby?
The median time from application to decision is 5.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Blaby consented?
609 MW has been consented across 5 approved schemes. A further 2 applications awaits a decision.
Other technologies in Blaby
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.