Battery storage planning in Warwick

Warwick has decided 5 battery storage schemes and approved 40% of them, taking a median of 4.9 months to decide. Consented capacity: 132 MW. 2 applications still awaiting a decision.

40%
Approved
2 granted · 3 refused
4.9 mo
Median decision
UK 6 mo
132 MW
Consented
50 MW refused
1
Appeals
1 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Warwick compares

Against the 137 UK authorities with 5+ battery storage decisions, Warwick sits in the 0th percentile for approval rate (52 points below the England average) and the 63rd percentile for speed.

Decisions by year

35Refused — 1 (2022)122Approved — 1 (2025)Refused — 1 (2025)225Refused — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Micro Energy Storage Unit, Kenilworth Road - Micro Energy Storage Facility
AMP Clean Energy · W/25/1475 · 2.7 mo to decide
0.2Application Refused2026-01-18
Fosse Way - Battery Storage
Staffordshire Solar 1 Limited · W/24/1404 · 7.2 mo to decide
Application Refused2025-05-22
Holly Lane Energy Park - Solar Farm & Battery Storage
Exagen · W/23/1358 · 16.6 mo to decide
75Awaiting Construction2025-01-30
Honiley Road - Solar Farm & Battery Storage
Enso Green Holdings Limited · W/22/1577
57Awaiting Construction2022-10-06
Banner Hill Farm, Banner Hill & Rouncil Lane - Battery Storage
Flexion Energy Storage UK Limited · W/22/0941 · 1.8 mo to decide
49.9Application Refused2022-09-30
Sherbourne - Solar Farm
Namene Solar · W/22/0997
Revised2022-09-08
Honiley Road - Battery Storage
Enso Green Holdings P Limited · W/21/2080
Revised2021-11-19

Does Warwick approve battery storage schemes?

Yes — of the 5 battery storage schemes Warwick has decided, 40% were approved (2 granted, 3 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Warwick?

The median time from application to decision is 4.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Warwick consented?

132 MW has been consented across 2 approved schemes, with 50 MW refused. A further 2 applications awaits a decision.

Other technologies in Warwick

Solar in WarwickOnshore wind in Warwick

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com