Battery storage planning in Redcar and Cleveland

Redcar and Cleveland has decided 5 battery storage schemes and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 266 MW. 3 applications still awaiting a decision.

100%
Approved
5 granted · 0 refused
1.8 mo
Median decision
UK 6 mo
266 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Redcar and Cleveland compares

Against the 137 UK authorities with 5+ battery storage decisions, Redcar and Cleveland sits in the 73rd percentile for approval rate (8 points above the England average) and the 97th percentile for speed.

Decisions by year

35Approved — 1 (2016)116Approved — 1 (2019)119Approved — 1 (2021)121Approved — 1 (2023)123Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Teesworks Battery Storage Project
Teesworks Ltd, NatPower UK · R/2024/0843/FFM
1000Application Withdrawn2025-08-26
Old Hall Farm, Lackenby - BESS
Lackenby Energy Limited · R/2025/0500/FFM
244Application Submitted2025-08-13
A171, Guisborough Woods - Battery Energy Storage System
Harmony MS Limited · R/2025/0456/FFM
28Application Submitted2025-07-16
Teesworks, Lackenby - Battery Energy Storage
South Tees Energy Storage Limited · R/2024/0866/FFM · 3 mo to decide
Awaiting Construction2025-03-25
Wilton International, Greystones Road - Phase 1
Sembcorp Utilities (UK) Limited · R/2023/0545/CL · 1.8 mo to decide
150Awaiting Construction2023-10-04
Greystones Road, Grangetown - Battery Energy Storage System
Sembcorp Utilities UK Limited · R/2021/0888/CL · 1.6 mo to decide
60Awaiting Construction2021-12-17
Lackenby
EDF Energy Renewables · R/2019/0433/FF · 3 mo to decide
49.9Planning Permission Expired2019-10-24
Lackenby
EDF Energy Renewables · R/2017/0564/FF
49.9Revised2017-08-17
Cleveland Potash
Kiwi Power · NYM/2015/0922/FL · 1.8 mo to decide
6Operational2016-03-02

Does Redcar and Cleveland approve battery storage schemes?

Yes — of the 5 battery storage schemes Redcar and Cleveland has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Redcar and Cleveland?

The median time from application to decision is 1.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Redcar and Cleveland consented?

266 MW has been consented across 5 approved schemes. A further 3 applications awaits a decision.

Other technologies in Redcar and Cleveland

Solar in Redcar and ClevelandOnshore wind in Redcar and Cleveland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.