Battery storage planning in Uttlesford

Uttlesford has decided 8 battery storage schemes and approved 88% of them, taking a median of 8 months to decide. Consented capacity: 59 MW. 3 applications still awaiting a decision.

88%
Approved
7 granted · 1 refused
8 mo
Median decision
UK 6 mo
59 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

How Uttlesford compares

Against the 137 UK authorities with 5+ battery storage decisions, Uttlesford sits in the 29th percentile for approval rate (4 points below the England average) and the 25th percentile for speed.

Decisions by year

35Approved — 2 (2022)222Approved — 2 (2023)223Approved — 1 (2024)124Approved — 1 (2025)125Refused — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Chelmsford Road, Great Dunmow - Micro Energy Storage
AMP Clean Energy · UTT/26/0113/FUL
0.2Application Submitted2026-01-19
Maggots End Road, Berden - Solar Farm & Battery Storage
Low Carbon Limited · UTT/25/1224/FUL · 8 mo to decide
Application Refused2026-01-15
Hales Farm - Battery Storage
Hales Farms Limited · UTT/24/3069/FUL · 1.6 mo to decide
Awaiting Construction2025-02-20
Wickham Hall Estate - Battery Storage
Endurance Energy Wickham Hall Limited · UTT/24/1417/PINS · 2.6 mo to decide
10Awaiting Construction2024-09-13
Felsted School Road - Solar Photovoltaic Farm & Battery storage
Clearstone Energy · UTT/22/0007/FUL · 31.9 mo to decide
Awaiting Construction2023-09-05
Hill Hall
Lightsource BP / LL Property Services · UTT/17/3037/FUL · 68.3 mo to decide
Planning Permission Expired2023-06-29
Chesterford Park - Green Energy Hub
Chesterford Park (General Partner) Limited · UTT/21/2846/FUL · 15.3 mo to decide
Awaiting Construction2022-12-23
Thaxted - Solar farm
Low Carbon Limited · UTT/21/1833/FUL · 15.7 mo to decide
Awaiting Construction2022-09-29
Wickham Hall Estate - Battery Storage
Endurance Energy Wickham Hall Limited · UTT/21/3108/FUL · 4.6 mo to decide
Revised2022-04-19
Maggots End Road, Berden - Solar Farm & Battery Storage
Low Carbon Limited · UTT/21/3356/FUL · 2.4 mo to decide
Revised2022-01-24
Pelham
Statera Energy/ InfraRed Capital · UTT/16/2316/FUL
49Operational2016-08-16

Does Uttlesford approve battery storage schemes?

Yes — of the 8 battery storage schemes Uttlesford has decided, 88% were approved (7 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Uttlesford?

The median time from application to decision is 8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Uttlesford consented?

59 MW has been consented across 7 approved schemes. A further 3 applications awaits a decision.

Other technologies in Uttlesford

Solar in UttlesfordOnshore wind in Uttlesford

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.