Novarly ParcelRenewable planning

Renewable planning Battery storageCheshire West and Chester

Battery storage planning in Cheshire West and Chester

Cheshire West and Chester has decided 11 battery storage schemes and approved 91% of them, taking a median of 9.2 months to decide. Consented capacity: 649 MW. 4 applications still awaiting a decision.

91%
Approved
10 granted · 1 refused
9.2 mo
Median decision
UK 6 mo
649 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

How Cheshire West and Chester compares

Against the 137 UK authorities with 5+ battery storage decisions, Cheshire West and Chester sits in the 36th percentile for approval rate (1 points below the England average) and the 17th percentile for speed.

Decisions by year

35Approved — 1 (2017)117Approved — 2 (2021)221Approved — 1 (2022)122Approved — 2 (2023)223Approved — 1 (2024)Refused — 1 (2024)224Approved — 3 (2025)325
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (15)

SchemeMWStatusDecided
Wallerscote Limebeds - Battery Energy Storage
Infinis Solar Developments Limited / Green Earth Developments · 23/02766/FUL · 22.6 mo to decide
30Awaiting Construction2025-07-21
Rectory Lane - Energy Storage System
Net Zero Eighteen Limited · 24/02219/FUL · 8.7 mo to decide
200Awaiting Construction2025-05-19
Electricity Substation, Bellevue Lane - Battery Storage
Coriolis Energy · 24/00935/FUL · 12.5 mo to decide
40Awaiting Construction2025-05-07
Aston Grange, Aston - Solar Panels & Battery Energy Storage System
Innova Renewables · 25/00100/FULEIA
6Application Submitted2025-02-24
Mollington - Battery Energy Storage
Qair Renewables UK Limited · 25/00132/FUL
240Application Submitted2025-01-17
Bell Meadow Business Park, Park Lane - Battery Storage
PPLS Partnership · 23/02390/FUL · 14.6 mo to decide
Application Refused2024-12-23
Portmanmoor Road Industrial Estate, Splott - Battery Storage Units
Infinis Energy Services Limited · 24/00935/FUL · 3 mo to decide
10Awaiting Construction2024-07-22
Ash Road, Elton - Battery Energy Storage
Beryl Street Generation Limited · 23/03900/FUL
Application Submitted2023-12-08
Capenhurst Lane, Capenhurst - Battery Storage
Aura Power BESS Limited · 22/03585/FUL · 14.5 mo to decide
100Awaiting Construction2023-12-08
Cheshire Power Station - Battery Storage Facility
RWE Generation UK Plc · 21/04501/FUL · 18.6 mo to decide
45Awaiting Construction2023-05-24
Capenhurst Lane, Capenhurst - Battery storage
HD888CAP Limited · 21/02404/FUL · 9.2 mo to decide
57Under Construction2022-03-11
Chads Farm - Photovoltaic Arrays & Battery Storage
Renewable Connections Developments Limited · 22/00224/FUL
522Application Submitted2022-02-21
Native River
Varco Energy · 20/04767/FUL · 3.9 mo to decide
57Operational2021-04-16
National Grid Electricity Substation, Capenhurst Lane - Battery Storage
Zenobe Energy Limited · 20/03681/FUL · 3.8 mo to decide
100Operational2021-02-01
Oil Sites Road
UK Power Reserve · 17/03414/FUL · 2.7 mo to decide
9.6Awaiting Construction2017-10-30

Does Cheshire West and Chester approve battery storage schemes?

Yes — of the 11 battery storage schemes Cheshire West and Chester has decided, 91% were approved (10 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Cheshire West and Chester?

The median time from application to decision is 9.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Cheshire West and Chester consented?

649 MW has been consented across 10 approved schemes. A further 4 applications awaits a decision.

Other technologies in Cheshire West and Chester

Solar in Cheshire West and ChesterOnshore wind in Cheshire West and Chester

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.