Battery storage planning in Cumberland

Cumberland has decided 11 battery storage schemes and approved 100% of them, taking a median of 4.2 months to decide. Consented capacity: 1,519 MW. 5 applications still awaiting a decision.

100%
Approved
11 granted · 0 refused
4.2 mo
Median decision
UK 6 mo
1,519 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Cumberland compares

Against the 137 UK authorities with 5+ battery storage decisions, Cumberland sits in the 73rd percentile for approval rate (8 points above the England average) and the 72nd percentile for speed.

Decisions by year

35Approved — 1 (2019)119Approved — 1 (2023)123Approved — 5 (2024)524Approved — 3 (2025)325
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
Cleator Energy Storage Facility Extension
Cleator Battery Storage Limited · 4/26/2022/0F1
5Application Submitted2026-01-22
Woodend And Moor Row, Egremont - Battery Energy Storage
JT Energy Storage (Windel Energy) · 4/25/2180/0F1 · 6.9 mo to decide
30Awaiting Construction2025-12-15
Harker Moss - Battery Energy Storage System
ESB (Harker) Limited · 24/0680 · 7.9 mo to decide
360Awaiting Construction2025-07-09
Ewanrigg Farmhouse, Ewanrigg - Battery Storage
Anesco Limited · FUL/2025/0080
Application Submitted2025-06-03
Netherhall Rugby Club -Micro Energy Storage Facility
AMP Energy Services Limited · FUL/2025/0032 · 2 mo to decide
0.2Awaiting Construction2025-05-13
Cargo Road, Cargo - Battery Storage
Immersa Limited · 23/0613 · 13.1 mo to decide
200Abandoned2024-10-17
West Farm, Aspatria - Battery Storage Facility
Net Zero Seventeen Limited · FUL/2024/0085 · 4.4 mo to decide
50Awaiting Construction2024-09-04
Low Harker Farm, Low Harker - Battery Storage Facility
Zenobe Energy Limited · 24/0093 · 5.2 mo to decide
400Awaiting Construction2024-07-18
Capon Tree Road - Battery Energy Storage
Prime Energy Limited · 24/0300 · 1.7 mo to decide
3Awaiting Construction2024-06-19
Todhills and Westlinton - Harker Battery Energy Storage Facility
Windel Energy · 23/0833 · 3.3 mo to decide
200Awaiting Construction2024-03-14
Grassing Rome Street - Battery Storage
STOR 141 Limited · 22/0513 · 20.3 mo to decide
15.5Awaiting Construction2024-03-07
Blackdyke Farm, Blackford - Battery Storage
Innova Renewables · 23/0444 · 3.5 mo to decide
400Awaiting Construction2023-10-05
Blackdyke Farm, Blackford - Battery Storage
Novus Renewable Services Limited / Story Construction · 23/0659
340Application Submitted2023-09-22
Cleator Energy Storage Facility Extension
Renewable Energy Systems · 4/22/2335/0F1 · 4 mo to decide
Revised2022-12-15
Pow Motey, Langrigg - Solar Panels & Batteries Storage
J W Gate & Son · REJ/2022/0003
Application Submitted2022-05-04
Harker Grid Sub Station
Pivot Power · 19/0371 · 2.1 mo to decide
49.9Planning Permission Expired2019-07-10
Blackdyke Farm Battery Storage Project
Low Carbon Storage Investment Company · 17/0616
49.9Abandoned2017-07-07
Cleator
Low Carbon Storage Investment Company/ VLC
10Operational

Does Cumberland approve battery storage schemes?

Yes — of the 11 battery storage schemes Cumberland has decided, 100% were approved (11 granted, 0 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Cumberland?

The median time from application to decision is 4.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Cumberland consented?

1,519 MW has been consented across 11 approved schemes. A further 5 applications awaits a decision.

Other technologies in Cumberland

Solar in CumberlandOnshore wind in Cumberland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.