Renewable planning › Battery storage › North East Derbyshire
Battery storage planning in North East Derbyshire
North East Derbyshire has decided 10 battery storage schemes and approved 60% of them, taking a median of 3.3 months to decide. Consented capacity: 47 MW.
How North East Derbyshire compares
Against the 137 UK authorities with 5+ battery storage decisions, North East Derbyshire sits in the 3rd percentile for approval rate (32 points below the England average) and the 82nd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (12)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Hallgate Farm - Battery Energy Storage Enray Power · 25/00703/MFL · 3.5 mo to decide | — | Awaiting Construction | 2025-12-11 |
The Electricity Substation, Baslow Road - Energy Storage System AMP Clean Energy · 25/00649/FL · 2.1 mo to decide | 0.2 | Application Refused | 2025-10-15 |
Lodge Farm, Calow - Battery Energy Storage System Enray Power · 24/01034/MFL · 8.3 mo to decide | 25 | Awaiting Construction | 2025-07-16 |
Eden Meadows, Stretton Road, Morton - Solar PV Panels & Battery Energy Storage System JBM Solar · 23/01089/FL · 17.2 mo to decide | — | Application Refused | 2025-05-22 |
Birkin Lane, Temple Normanton - Battery Storage GridSource Limited · 24/00707/FL · 3.1 mo to decide | — | Application Refused | 2024-12-20 |
Dyche Lane, Batemoor - Battery Energy Storage System Ylem Energy Limited · 24/00035/FL · 4.7 mo to decide | — | Application Refused | 2024-06-28 |
Westthorpe Fields Road, Killamarsh - Battery Storage Amp Clean Energy · 23/00283/FL · 2.9 mo to decide | 0.2 | Awaiting Construction | 2023-06-22 |
Alfreton Solar Farm Kronos Solar · 20/01282/FL | 25 | Application Withdrawn | 2022-03-18 |
Magnavale Limited - Renewable energy plant Magnavale Limited · 21/00693/FL · 3 mo to decide | 0.15 | Awaiting Construction | 2021-08-20 |
Calow Green Farm Arlington Energy (formerly Enso Energy) · 18/01011/FL · 18.7 mo to decide | 20 | Operational | 2020-03-31 |
Smithybrook View Together Housing · 18/00134/FL · 3.1 mo to decide | 1.2 | Planning Permission Expired | 2018-05-24 |
Callywhite Lane Commercial Estate Volta Energy Storage · 17/01072/FL | 18 | Abandoned | 2017-10-12 |
Does North East Derbyshire approve battery storage schemes?
Yes — of the 10 battery storage schemes North East Derbyshire has decided, 60% were approved (6 granted, 4 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in North East Derbyshire?
The median time from application to decision is 3.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has North East Derbyshire consented?
47 MW has been consented across 6 approved schemes. There are no applications currently awaiting a decision.
Other technologies in North East Derbyshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.