Novarly ParcelRenewable planning

Renewable planning Battery storageOldham

Battery storage planning in Oldham

Oldham has decided 5 battery storage schemes and approved 100% of them, taking a median of 3.1 months to decide. Consented capacity: 110 MW. 1 application still awaiting a decision.

100%
Approved
5 granted · 0 refused
3.1 mo
Median decision
UK 6 mo
110 MW
Consented
across approved schemes
1
Appeals
1 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Oldham compares

Against the 137 UK authorities with 5+ battery storage decisions, Oldham sits in the 73rd percentile for approval rate (8 points above the England average) and the 85th percentile for speed.

Decisions by year

35Approved — 1 (2020)120Approved — 3 (2022)322Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (6)

SchemeMWStatusDecided
Medlock Road, Failsworth - Battery Energy Storage
Root Power (North) Limited · FUL/353405/24 · 12.4 mo to decide
30Awaiting Construction2025-10-21
Lowerfields Farm, Warren Lane - Battery Energy Storage System
Renewable Connections Developments Limited · FUL/354740/25
27Application Submitted2025-07-24
Chadderton - Battery energy storage facility
Field · FUL/348758/22 · 8 mo to decide
20Under Construction2022-12-09
Whitegate Battery Storage
Pelagic Energy (Constantine Energy) · FUL/348501/22 · 3.1 mo to decide
57Under Construction2022-05-19
Chadderton - Battery Storage System
Zetex Plc · FUL/348617/22 · 2.1 mo to decide
2.5Awaiting Construction2022-05-05
Bentfield Industrial Units
Diodes Zetex Semiconductors · PA/344529/20 · 2.7 mo to decide
0.3Awaiting Construction2020-05-05

Does Oldham approve battery storage schemes?

Yes — of the 5 battery storage schemes Oldham has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Oldham?

The median time from application to decision is 3.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Oldham consented?

110 MW has been consented across 5 approved schemes. A further 1 application awaits a decision.

Other technologies in Oldham

Solar in OldhamOnshore wind in Oldham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.