Novarly ParcelRenewable planning

Renewable planning Battery storageThe Planning Inspectorate - National Infrastructure

Battery storage planning in The Planning Inspectorate - National Infrastructure

The Planning Inspectorate - National Infrastructure has decided 19 battery storage schemes and approved 100% of them, taking a median of 17.4 months to decide. Consented capacity: 706 MW. 11 applications still awaiting a decision.

100%
Approved
19 granted · 0 refused
17.4 mo
Median decision
UK 6 mo
706 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How The Planning Inspectorate - National Infrastructure compares

Against the 137 UK authorities with 5+ battery storage decisions, The Planning Inspectorate - National Infrastructure sits in the 73rd percentile for approval rate (8 points above the England average) and the 1st percentile for speed.

Decisions by year

510Approved — 1 (2018)118Approved — 2 (2020)220Approved — 2 (2022)222Approved — 1 (2023)123Approved — 2 (2024)224Approved — 9 (2025)925Approved — 2 (2026)226
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (31)

SchemeMWStatusDecided
Springwell, Lincoln - Springwell Solar Farm & Battery Storage
EDF Energy Renewables · EN010149 · 15.6 mo to decide
Awaiting Construction2026-04-08
Fenwick Solar Farm & Battery Storage
Boom Developments Limited · EN010152 · 15.6 mo to decide
Awaiting Construction2026-02-18
Helios Renewable Energy Project
Enso Green Holdings D Limited · EN010140 · 17 mo to decide
Awaiting Construction2025-12-03
Stonestreet Green - Solar Farm & Battery Storage
Evolution Power · EN010135 · 15.5 mo to decide
Awaiting Construction2025-10-23
Tillbridge Solar Farm, Hemswell - Battery Storage
Tillbridge Solar Limited · EN010142 · 18.1 mo to decide
Awaiting Construction2025-10-14
The Tween Bridge Solar Farm
RWE · EN010148
400Application Submitted2025-08-26
Byers Gill Solar Farm
JBM Solar Projects Limited · EN010139 · 17.4 mo to decide
Awaiting Construction2025-07-23
Fosse Green Energy
Windel Energy / Canadian Solar · EN010154
Application Submitted2025-07-18
Great North Road Solar Park
Elements Green · EN010162
Application Submitted2025-06-27
Green Hill Solar Farm & Battery Storage
Island Green Power · EN010170
600Application Submitted2025-06-19
Oaklands Solar Farm Project - Solar Farm & Battery Storage
BayWa r.e. UK Limited · EN010122 · 16.3 mo to decide
37.5Awaiting Construction2025-06-19
Frodsham Solar Project & Battery Storage
Cubico Renewables · EN010153
100Application Submitted2025-05-30
Steeple Renewables Project
Renewable Energy Systems RES Limited (Beaufort) · EN010163
150Application Submitted2025-05-14
East Yorkshire Solar Farm
Boom Power · EN010143 · 17.6 mo to decide
Awaiting Construction2025-05-09
Beacon Fen Energy Park
Low Carbon Limited · EN010151
600Application Submitted2025-04-08
Dean Moor Solar Farm & Battery Storage
Firma Energy / IB Vogt · EN010155
Application Submitted2025-03-26
North Lincolnshire Green Energy Park
Solar 21 Renewable Energy Limited · EN010116 · 33.4 mo to decide
30Awaiting Construction2025-03-13
One Earth Solar Farm
Orsted UK Limited / PS Renewables · EN010159
Application Submitted2025-02-27
Peartree Hill Solar Farm
JBM Solar / RWE · EN010157
Application Submitted2025-02-21
Heckington Fen Solar Park - Battery Storage
Ecotricity Limited · EN010123 · 23.3 mo to decide
Awaiting Construction2025-01-24
West Burton Solar Project
Island Green Power · EN010132 · 22.2 mo to decide
20Awaiting Construction2025-01-24
Gate Burton - Solar & Energy Storage Park
Low Carbon · EN010131 · 17.5 mo to decide
Awaiting Construction2024-07-12
Sunnica Energy Farm (East and West)
Sunnica · EN010106 · 31.8 mo to decide
8.8Awaiting Construction2024-07-12
Longfield
Longfield Solar Energy Farm Limited (part of EDF Renwables) · EN010118 · 15.9 mo to decide
Awaiting Construction2023-06-26
Cottam Solar Project
Island Green Power · EN010133
Application Submitted2023-01-12
Little Crow Solar Park
INRG Solar · EN010101 · 16 mo to decide
90Awaiting Construction2022-04-05
Thurrock Flexible Generation Plant
Thurrock Power · EN010092 · 20.2 mo to decide
150Operational2022-02-16
Cleve Hill Solar Project
Quinbrook Infrastructure Partners · EN010085 · 18.4 mo to decide
150Operational2020-05-28
Riverside Energy Park
Cory Riverside Energy · EN010093 · 16.8 mo to decide
20Awaiting Construction2020-04-09
Drax Re-Power
Drax Group · 2.8 mo to decide
200Awaiting Construction2018-05-24
Tilbury Energy Centre
RWE Generation
100Abandoned2018-02-20

Does The Planning Inspectorate - National Infrastructure approve battery storage schemes?

Yes — of the 19 battery storage schemes The Planning Inspectorate - National Infrastructure has decided, 100% were approved (19 granted, 0 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in The Planning Inspectorate - National Infrastructure?

The median time from application to decision is 17.4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has The Planning Inspectorate - National Infrastructure consented?

706 MW has been consented across 19 approved schemes. A further 11 applications awaits a decision.

Other technologies in The Planning Inspectorate - National Infrastructure

Solar in The Planning Inspectorate - National InfrastructureOnshore wind in The Planning Inspectorate - National Infrastructure

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.