Battery storage planning in Winchester

Winchester has decided 9 battery storage schemes and approved 89% of them, taking a median of 5.1 months to decide. Consented capacity: 146 MW. 1 application still awaiting a decision.

89%
Approved
8 granted · 1 refused
5.1 mo
Median decision
UK 6 mo
146 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Winchester compares

Against the 137 UK authorities with 5+ battery storage decisions, Winchester sits in the 33rd percentile for approval rate (3 points below the England average) and the 61st percentile for speed.

Decisions by year

35Approved — 3 (2017)317Approved — 1 (2020)120Approved — 1 (2024)124Approved — 2 (2025)Refused — 1 (2025)325Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (12)

SchemeMWStatusDecided
Titchfield Lane, Wickham - Battery Energy Storage System
Grenergy Renewables · 24/02818/FUL · 14.7 mo to decide
Awaiting Construction2026-03-27
Glebe Farm, Curdridge Lane - Battery Energy Storage System
Glebe Farm Energy Limited · 25/01050/FUL
Application Submitted2025-05-22
Silkstead Farm, Poles Lane - Battery Energy Storage System
Winchester Energy Reserve Limited · 24/01007/FUL · 9.2 mo to decide
49.9Awaiting Construction2025-03-13
Ash Farm, Titchfield Lane - Battery Storage
Botley Energy Reserve 2 Limited · 23/01106/FUL · 21.6 mo to decide
15Awaiting Construction2025-02-19
Hawks Nest Farm - Battery Storage
GridSource Limited · 24/01758/FUL · 2.2 mo to decide
Application Refused2025-01-09
IBM Hursley - Battery Storage
IBM UK Limited · 23/02836/FUL · 3.4 mo to decide
1.5Awaiting Construction2024-06-19
Three Maids Hill Solar Farm
Environmental Asset Management · 20/02311/FUL · 6.9 mo to decide
Abandoned2021-05-19
Titchfield Lane
Balanced Grid Solutions · 19/02710/FUL · 8.5 mo to decide
49Under Construction2020-08-20
Lovedean Substation
Pivot Power · 19/01071/FUL
49.9Application Withdrawn2020-01-24
Sparsholt college
Sparsholt College (formerly Ecotricity) · 17/02485/FUL · 2.8 mo to decide
2Planning Permission Expired2017-12-20
Stockbridge Road
Winchester Power · 17/02575/FUL · 2.3 mo to decide
10Awaiting Construction2017-12-14
Winchester Battery Storage
Conrad Energy · 17/01044/FUL · 2.5 mo to decide
19Operational2017-06-23

Does Winchester approve battery storage schemes?

Yes — of the 9 battery storage schemes Winchester has decided, 89% were approved (8 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Winchester?

The median time from application to decision is 5.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Winchester consented?

146 MW has been consented across 8 approved schemes. A further 1 application awaits a decision.

Other technologies in Winchester

Solar in WinchesterOnshore wind in Winchester

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.