Novarly ParcelRenewable planning

Renewable planning Battery storageSouth Staffordshire

Battery storage planning in South Staffordshire

South Staffordshire has decided 22 battery storage schemes and approved 91% of them, taking a median of 7.3 months to decide. Consented capacity: 870 MW. 2 applications still awaiting a decision.

91%
Approved
20 granted · 2 refused
7.3 mo
Median decision
UK 6 mo
870 MW
Consented
100 MW refused
2
Appeals
2 allowed on appeal

How South Staffordshire compares

Against the 137 UK authorities with 5+ battery storage decisions, South Staffordshire sits in the 36th percentile for approval rate (1 points below the England average) and the 30th percentile for speed.

Decisions by year

815Approved — 1 (2016)116Approved — 3 (2022)322Approved — 5 (2024)524Approved — 10 (2025)Refused — 2 (2025)1225Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (25)

SchemeMWStatusDecided
Innovation Drive, Bilbrook - Micro Energy Storage Project
AMP Clean Energy · 25/00847/FUL · 3 mo to decide
0.2Awaiting Construction2026-01-08
Orchard Farm, Langley Road - Battery Energy Storage System
RE Projects Development Limited · 24/01102/FULM · 11.2 mo to decide
100Application Refused2025-12-22
Ebstree Road, Trysull, Seisdon - Battery Energy Storage
NZED Projectco 3 limited · 25/00431/FULM · 5.8 mo to decide
99.9Awaiting Construction2025-11-21
Saxon Road - Micro Energy Storage Facility
AMP Energy Services Limited · 25/00302/FUL · 5.3 mo to decide
0.2Application Refused2025-09-04
Chillington Estate, Chillington Park - Battery Storage
Elgin Energy Esco Limited · 23/00576/FULM · 20.2 mo to decide
40Awaiting Construction2025-07-25
Pool Hall Farm, Lower Penn - Battery Storage
Elgin Energy Esco Limited · 24/01092/FULM · 6.4 mo to decide
100Awaiting Construction2025-07-21
Energyst Rental Solutions, Station Road - Micro Energy Storage Facility
AMP Clean Energy · 25/00372/FUL · 2.7 mo to decide
0.2Awaiting Construction2025-07-18
Canalside - Battery Storage System
Greenfield Energy Developments Limited / Renewable Power Capital · 24/00951/FULM · 8 mo to decide
60Awaiting Construction2025-07-14
Wombourne Road, Wombourne - Battery Energy Storage System
Pathfinder Clean Energy UK Dev Limited · 24/01093/FULM · 5.3 mo to decide
49.5Awaiting Construction2025-05-29
Hinksford Substation, Hinksford Lane - Battery Energy Storage
Balance Power Projects Limited · 24/00190/FULM · 12.3 mo to decide
49.99Awaiting Construction2025-03-06
Energyst Rental Solutions, Station Road - Micro Energy Storage Facility
AMP Clean Energy · 24/00885/FUL · 3.7 mo to decide
Revised2025-02-20
Hobble Lane, Great Wyrley - Battery Energy Storage
Anglo ES Great Wyrley Limited · 24/00010/FULM · 13.5 mo to decide
49.9Awaiting Construction2025-02-20
Latherford Close, Four Ashes - Micro Energy Storage
AMP Clean Energy · 24/00886/FUL · 4.4 mo to decide
0.2Awaiting Construction2025-02-20
Element Court, Hilton Cross Business Park - Micro Energy Storage Facility
AMP Clean Energy · 24/00887/FUL · 3.8 mo to decide
0.2Awaiting Construction2025-02-14
Levedale Road, Levedale - Battery Energy Storage
Anglo Renewables Limited · 23/00145/FUL · 20.6 mo to decide
50Awaiting Construction2024-12-06
New Road, Featherstone - Battery Storage
Chiltern Renewables Hockliffe Limited · 23/01031/OUTM
100Application Withdrawn2024-11-25
Ebstree Road, Trysull - Battery Energy Storage
Bengrove Bess Limited · 23/00980/FULM · 11.5 mo to decide
49.9Awaiting Construction2024-11-21
Bognop Road, Essington - Solar Farm & Battery Energy Storage
Intelligent Alternatives Limited · 24/00556/FULM
Application Submitted2024-11-14
Upper Latherford Farm, Latherford Lane - Battery Energy Storage System
Net Zero Twelve Limited · 23/00883/FUL · 11.4 mo to decide
50Awaiting Construction2024-10-16
Oaklands Farm, New Road - Battery Energy Storage
Conrad Energy (Developments) II Limited · 23/01044/FULM · 8 mo to decide
70Awaiting Construction2024-08-22
Four Ashes, Deepmore Lane - Solar Farm
Renewable Connections · 23/00931/FULM · 8.5 mo to decide
Awaiting Construction2024-07-17
Penstone Lane, Lower Penn 2 - Battery Storage
Anglo Renewables Limited · 22/00045/FUL · 7.3 mo to decide
50Awaiting Construction2022-09-29
Penstone Lane, Penn 1 - Battery Storage Facility
Anglo Renewables Limited · 22/00044/FUL · 7.3 mo to decide
50Awaiting Construction2022-09-28
South Staffordshire Railway Walk, Castlecroft - Battery Storage
Balance Power Projects Limited · 21/00440/FUL · 15.1 mo to decide
50Awaiting Construction2022-08-16
Wolverhampton West Sub Station
Statera Energy · 16/00747/FUL · 2 mo to decide
50Planning Permission Expired2016-10-21

Does South Staffordshire approve battery storage schemes?

Yes — of the 22 battery storage schemes South Staffordshire has decided, 91% were approved (20 granted, 2 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in South Staffordshire?

The median time from application to decision is 7.3 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has South Staffordshire consented?

870 MW has been consented across 20 approved schemes, with 100 MW refused. A further 2 applications awaits a decision.

Other technologies in South Staffordshire

Solar in South StaffordshireOnshore wind in South Staffordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.