Battery storage planning in Argyll and Bute

Argyll and Bute has decided 5 battery storage schemes and approved 80% of them, taking a median of 9.5 months to decide. Consented capacity: 80 MW.

80%
Approved
4 granted · 1 refused
9.5 mo
Median decision
UK 6 mo
80 MW
Consented
50 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Argyll and Bute compares

Against the 137 UK authorities with 5+ battery storage decisions, Argyll and Bute sits in the 10th percentile for approval rate (12 points below the England average) and the 14th percentile for speed.

Decisions by year

35Approved — 1 (2021)121Approved — 1 (2023)123Refused — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
SSE Taynuilt Substation - Battery Energy Storage
Downing Energy Development Company Limited · 24/02083/PP · 11.3 mo to decide
49.9Awaiting Construction2025-11-14
Ardencaple Farm - Battery Storage
Ylem Energy Limited · 23/02472/PP · 7.8 mo to decide
49.99Application Refused2024-10-24
Ardnadam Electricity Sub Station, Sandbank - Battery Energy Storage Facility
Flexion Energy UK Storage · 22/01788/PP · 7.5 mo to decide
Awaiting Construction2023-05-05
Drumfad Wood
Capbal · 18/01749/PPP · 29 mo to decide
29.9Planning Permission Expired2021-03-24
Gigha Wind Farm Battery Project
Gigha Island community (Multiple Owners)
0.1Decommissioned

Does Argyll and Bute approve battery storage schemes?

Yes — of the 5 battery storage schemes Argyll and Bute has decided, 80% were approved (4 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Argyll and Bute?

The median time from application to decision is 9.5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Argyll and Bute consented?

80 MW has been consented across 4 approved schemes, with 50 MW refused. There are no applications currently awaiting a decision.

Other technologies in Argyll and Bute

Solar in Argyll and ButeOnshore wind in Argyll and Bute

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.