Battery storage planning in Wychavon
Wychavon has decided 12 battery storage schemes and approved 100% of them, taking a median of 5.7 months to decide. Consented capacity: 44 MW. 6 applications still awaiting a decision.
How Wychavon compares
Against the 137 UK authorities with 5+ battery storage decisions, Wychavon sits in the 73rd percentile for approval rate (8 points above the England average) and the 51st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (19)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Bishampton Solar Energy Park, Broad Lane - Battery Energy Storage Infinis Energy Storage Limited · W/25/00943/FUL · 6.4 mo to decide | — | Awaiting Construction | 2025-11-13 |
Copcut Lane, Copcut -Micro Energy Storage System AMP Clean Energy · W/25/01217/FUL · 1.8 mo to decide | 0.2 | Awaiting Construction | 2025-10-27 |
Fibden Farm, Hampton Lovett - Battery Energy Storage System Grenergy Renewables · W/24/01088/FUL · 13.5 mo to decide | — | Awaiting Construction | 2025-07-29 |
Home Farm Canadian Solar / Novergy · W/23/01011/FUL · 23.7 mo to decide | — | Awaiting Construction | 2025-06-16 |
Home Farm Canadian Solar / Novergy · 23/00499/FUL · 22.7 mo to decide | — | Awaiting Construction | 2025-05-16 |
Worcester Rugby Football Club, Hindlip - Micro Energy Storage Facility AMP Clean Energy · W/25/00211/FUL · 1.6 mo to decide | 0.2 | Awaiting Construction | 2025-03-24 |
Worcester Rugby Football Club, Hindlip - Micro Energy Storage Facility AMP Clean Energy · W/24/01766/FUL · 3.6 mo to decide | 0.2 | Revised | 2024-12-23 |
Fibden Farm - Battery Storage Facility Grenergy Renewables · W/24/01088/FUL | — | Application Submitted | 2024-06-14 |
Pershore Lane, Tibberton - Battery Energy Storage System Sirius Renewable Energy · W/22/02717/FUL · 10.2 mo to decide | 14 | Awaiting Construction | 2023-10-27 |
Greenfields Farm, Worcester Road - Battery Energy Storage Mercia Power Response Limited · W/23/00775/FUL · 4.9 mo to decide | — | Awaiting Construction | 2023-09-22 |
Lincomb Farm - Battery Storage Facility EL Asset Co.1 Limited · W/23/01540/FUL | — | Application Submitted | 2023-09-05 |
Droitwich Road, Martin Hussingtree - Solar Park Ecotricity Limited · W/23/00893/FUL | — | Application Submitted | 2023-05-19 |
Roundhill, Earls Common Road, Stock Green - Solar Farm JBM Solar Projects 11 Limited · W/23/00270/FUL | — | Application Submitted | 2023-02-23 |
Rectory Farm, Rectory Lane - Battery Storage Tag Energy · W/22/02326/FUL · 3.2 mo to decide | 30 | Awaiting Construction | 2023-02-20 |
Worcester Road, Wychbold - Battery Storage Hut Webbs Garden Centre · W/22/00583/FUL · 7.4 mo to decide | — | Awaiting Construction | 2022-10-28 |
Lower Strensham - Battery Energy Storage Next Energy · W/22/01432/FUL · 1.7 mo to decide | — | Awaiting Construction | 2022-09-08 |
Doverdale - Solar Farm & Battery Storage RWE · 21/01363/FUL · 6.7 mo to decide | 49.9 | Application Submitted | 2022-01-13 |
Littleton Solar Farm Stark Energy / SSE Renewables · 20/01798/FUL · 3.9 mo to decide | — | Operational | 2021-01-06 |
Bishampton Solar Farm Infinis · 20/02071/FUL | 8.8 | Abandoned | 2020-10-13 |
Does Wychavon approve battery storage schemes?
Yes — of the 12 battery storage schemes Wychavon has decided, 100% were approved (12 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Wychavon?
The median time from application to decision is 5.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Wychavon consented?
44 MW has been consented across 12 approved schemes. A further 6 applications awaits a decision.
Other technologies in Wychavon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.