Renewable planning Battery storageWelsh Government (NSIP)

Battery storage planning in Welsh Government (NSIP)

Welsh Government (NSIP) has decided 15 battery storage schemes and approved 80% of them, taking a median of 16.7 months to decide. Consented capacity: 181 MW. 7 applications still awaiting a decision.

80%
Approved
12 granted · 3 refused
16.7 mo
Median decision
UK 6 mo
181 MW
Consented
across approved schemes
1
Appeals
0 allowed on appeal

How Welsh Government (NSIP) compares

Against the 137 UK authorities with 5+ battery storage decisions, Welsh Government (NSIP) sits in the 10th percentile for approval rate (12 points below the England average) and the 3rd percentile for speed.

Decisions by year

510Approved — 1 (2019)119Approved — 2 (2022)Refused — 1 (2022)322Approved — 1 (2023)123Approved — 4 (2024)424Approved — 4 (2025)Refused — 2 (2025)625
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (22)

SchemeMWStatusDecided
White House Farm
Qair UK · CAS-03107-C5X9W1
12Application Submitted2025-12-30
Y Bryn Wind Farm
ESB / Coriolis Energy · DNS/3264571 · 23.1 mo to decide
Application Refused2025-11-21
Mynydd Maen Solar Farm (Cil-Lonydd)
Cenin Renewables Limited · DNS CAS-02446-R8X8W2 · 15.8 mo to decide
35Awaiting Construction2025-11-12
Craig y Perthi Solar Farm
JBM Solar Projects Limited · DNS/3279787 · 18.3 mo to decide
Application Refused2025-10-21
Alwen Forest Project
RWE Generation / Innogy · DNS/3214855 · 12.4 mo to decide
Awaiting Construction2025-10-02
Alaw M�n Solar Farm - Solar Farm & Energy Storage Facility
Enso Energy Limited · DNS/3274702 · 15.3 mo to decide
Awaiting Construction2025-08-26
Gaerwen Wind Farm
RWE Renewables UK Limited · DNS/3276735
Application Submitted2025-07-30
Land at Pen Onn - Solar Farm
Iolo Energy · DNS/3273713 · 17.3 mo to decide
Awaiting Construction2025-05-29
Pentre Bach Solar Farm
Elgin Energy EsCo Ltd · DNS/3239190
Application Submitted2025-01-09
Parc Solar Caenewydd
Infinis Solar Developments · CAS-01900-V0J7C7 · 5.7 mo to decide
46Awaiting Construction2024-12-02
Garn Fach Wind Farm
EDF Renewables · DNS/3244499 · 29 mo to decide
50Awaiting Construction2024-10-22
Abertillery - Wind farm - Battery
RWE Renewables UK Limited · DNS/3278009
Application Submitted2024-10-11
Plas Power Estate Solar Farm
Lightsource BP · DNS/3253253
57Application Submitted2024-06-11
Vianshill Farm, Parc Dyffryn - Solar Farm & Battery Storage
Cenin Renewables Limited · DNS/3267575 · 19.6 mo to decide
Awaiting Construction2024-05-23
Pancross & Oaklands Solar Farm
Infinis · DNS/3245504 · 12.6 mo to decide
50Awaiting Construction2024-05-23
Bretton Hall Solar Farm (Wales)
YnNi Newydd (New Energy Co-op) · DNS/3251545 · 17.4 mo to decide
Awaiting Construction2023-12-19
Brynwell Farm
Brynwell Farm Solar Limited · DNS/3261558 · 18.7 mo to decide
Awaiting Construction2022-11-10
Upper Ogmore Wind Farm
RES UK & Ireland Limited · DNS/3213662 · 22.6 mo to decide
Awaiting Construction2022-09-22
Elwy Solar Energy Farm
Statkraft UK Limited · DNS/3247619 · 15.3 mo to decide
Application Refused2022-07-01
Wentlooge Renewable Energy Hub
Wentlooge Farmers' Solar Scheme · CAS-01772-Z5P5D2
Appeal Lodged2022-06-20
Wentlooge Renewable Energy Hub
Wentlooge Farmers' Solar Scheme · DNS/3216558 · 16.1 mo to decide
62.5Revised2021-09-10
Llanwern Solar Farm & Battery Storage
NextEnergy Capital LLP · DNS/3213968 · 13.9 mo to decide
Operational2019-04-18

Does Welsh Government (NSIP) approve battery storage schemes?

Yes — of the 15 battery storage schemes Welsh Government (NSIP) has decided, 80% were approved (12 granted, 3 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Welsh Government (NSIP)?

The median time from application to decision is 16.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Welsh Government (NSIP) consented?

181 MW has been consented across 12 approved schemes. A further 7 applications awaits a decision.

Other technologies in Welsh Government (NSIP)

Solar in Welsh Government (NSIP)Onshore wind in Welsh Government (NSIP)

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.