Renewable planning › Battery storage › Welsh Government (NSIP)
Battery storage planning in Welsh Government (NSIP)
Welsh Government (NSIP) has decided 15 battery storage schemes and approved 80% of them, taking a median of 16.7 months to decide. Consented capacity: 181 MW. 7 applications still awaiting a decision.
How Welsh Government (NSIP) compares
Against the 137 UK authorities with 5+ battery storage decisions, Welsh Government (NSIP) sits in the 10th percentile for approval rate (12 points below the England average) and the 3rd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (22)
| Scheme | MW | Status | Decided |
|---|---|---|---|
White House Farm Qair UK · CAS-03107-C5X9W1 | 12 | Application Submitted | 2025-12-30 |
Y Bryn Wind Farm ESB / Coriolis Energy · DNS/3264571 · 23.1 mo to decide | — | Application Refused | 2025-11-21 |
Mynydd Maen Solar Farm (Cil-Lonydd) Cenin Renewables Limited · DNS CAS-02446-R8X8W2 · 15.8 mo to decide | 35 | Awaiting Construction | 2025-11-12 |
Craig y Perthi Solar Farm JBM Solar Projects Limited · DNS/3279787 · 18.3 mo to decide | — | Application Refused | 2025-10-21 |
Alwen Forest Project RWE Generation / Innogy · DNS/3214855 · 12.4 mo to decide | — | Awaiting Construction | 2025-10-02 |
Alaw M�n Solar Farm - Solar Farm & Energy Storage Facility Enso Energy Limited · DNS/3274702 · 15.3 mo to decide | — | Awaiting Construction | 2025-08-26 |
Gaerwen Wind Farm RWE Renewables UK Limited · DNS/3276735 | — | Application Submitted | 2025-07-30 |
Land at Pen Onn - Solar Farm Iolo Energy · DNS/3273713 · 17.3 mo to decide | — | Awaiting Construction | 2025-05-29 |
Pentre Bach Solar Farm Elgin Energy EsCo Ltd · DNS/3239190 | — | Application Submitted | 2025-01-09 |
Parc Solar Caenewydd Infinis Solar Developments · CAS-01900-V0J7C7 · 5.7 mo to decide | 46 | Awaiting Construction | 2024-12-02 |
Garn Fach Wind Farm EDF Renewables · DNS/3244499 · 29 mo to decide | 50 | Awaiting Construction | 2024-10-22 |
Abertillery - Wind farm - Battery RWE Renewables UK Limited · DNS/3278009 | — | Application Submitted | 2024-10-11 |
Plas Power Estate Solar Farm Lightsource BP · DNS/3253253 | 57 | Application Submitted | 2024-06-11 |
Vianshill Farm, Parc Dyffryn - Solar Farm & Battery Storage Cenin Renewables Limited · DNS/3267575 · 19.6 mo to decide | — | Awaiting Construction | 2024-05-23 |
Pancross & Oaklands Solar Farm Infinis · DNS/3245504 · 12.6 mo to decide | 50 | Awaiting Construction | 2024-05-23 |
Bretton Hall Solar Farm (Wales) YnNi Newydd (New Energy Co-op) · DNS/3251545 · 17.4 mo to decide | — | Awaiting Construction | 2023-12-19 |
Brynwell Farm Brynwell Farm Solar Limited · DNS/3261558 · 18.7 mo to decide | — | Awaiting Construction | 2022-11-10 |
Upper Ogmore Wind Farm RES UK & Ireland Limited · DNS/3213662 · 22.6 mo to decide | — | Awaiting Construction | 2022-09-22 |
Elwy Solar Energy Farm Statkraft UK Limited · DNS/3247619 · 15.3 mo to decide | — | Application Refused | 2022-07-01 |
Wentlooge Renewable Energy Hub Wentlooge Farmers' Solar Scheme · CAS-01772-Z5P5D2 | — | Appeal Lodged | 2022-06-20 |
Wentlooge Renewable Energy Hub Wentlooge Farmers' Solar Scheme · DNS/3216558 · 16.1 mo to decide | 62.5 | Revised | 2021-09-10 |
Llanwern Solar Farm & Battery Storage NextEnergy Capital LLP · DNS/3213968 · 13.9 mo to decide | — | Operational | 2019-04-18 |
Does Welsh Government (NSIP) approve battery storage schemes?
Yes — of the 15 battery storage schemes Welsh Government (NSIP) has decided, 80% were approved (12 granted, 3 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Welsh Government (NSIP)?
The median time from application to decision is 16.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Welsh Government (NSIP) consented?
181 MW has been consented across 12 approved schemes. A further 7 applications awaits a decision.
Other technologies in Welsh Government (NSIP)
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.