Battery storage planning in Hart

Hart has decided 8 battery storage schemes and approved 88% of them, taking a median of 9.1 months to decide. Consented capacity: 356 MW. 1 application still awaiting a decision.

88%
Approved
7 granted · 1 refused
9.1 mo
Median decision
UK 6 mo
356 MW
Consented
100 MW refused
1
Appeals
1 allowed on appeal

How Hart compares

Against the 137 UK authorities with 5+ battery storage decisions, Hart sits in the 29th percentile for approval rate (4 points below the England average) and the 18th percentile for speed.

Decisions by year

35Approved — 3 (2021)321Approved — 2 (2023)223Approved — 1 (2024)124Approved — 1 (2025)125Refused — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (10)

SchemeMWStatusDecided
Bowenhurst Farm, Mill Lane - Battery Energy Storage
Bowenhurst BESS Limited · 25/01186/FUL · 7.5 mo to decide
100Application Refused2026-02-27
Crondall Road, Crondall - Fleet Bramley Battery Energy Storage
Cragside Energy Limited · 24/02491/FUL · 7.4 mo to decide
99.9Awaiting Construction2025-08-22
Coxmoor Wood, Crondall Road - Battery Storage
Fleet Green Limited · 23/00823/FUL · 12.6 mo to decide
57Awaiting Construction2024-04-22
Blue Bell Lodge, Rye Common Lane - Battery Storage
Pulse Clean Energy · 22/02917/FUL · 3.7 mo to decide
49.5Awaiting Construction2023-05-22
Penn Croft Farm, Crondall - Battery Energy Storage Facility
Fleet BESS Limited & SSE Energy Solutions Limited · 21/02937/FUL · 13.5 mo to decide
100Awaiting Construction2023-01-30
Chosley Farm, North Warnborough Solar Farm and Battery storage
Shell Renewables (CSE23 Limited) · 20/03185/FUL · 9.7 mo to decide
Awaiting Construction2021-11-11
Bunkers Hill Farm - Solar farm & Battery stations
Vantage RE · 21/00552/FUL · 8.5 mo to decide
Under Construction2021-11-11
Rye Common
Pulse Clean Energy · 20/00651/FUL · 18.6 mo to decide
49.5Awaiting Construction2021-09-28
Fleet Substation
Pivot Power · 19/01186/FUL
49.9Application Withdrawn2019-12-30
Rye Common Lane
Harmony Energy · 18/01114/FUL
49.5Revised2018-08-30

Does Hart approve battery storage schemes?

Yes — of the 8 battery storage schemes Hart has decided, 88% were approved (7 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Hart?

The median time from application to decision is 9.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Hart consented?

356 MW has been consented across 7 approved schemes, with 100 MW refused. A further 1 application awaits a decision.

Other technologies in Hart

Solar in HartOnshore wind in Hart

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.