Renewable planning › Battery storage › South Holland
Battery storage planning in South Holland
South Holland has decided 13 battery storage schemes and approved 92% of them, taking a median of 3.5 months to decide. Consented capacity: 601 MW. 2 applications still awaiting a decision.
How South Holland compares
Against the 137 UK authorities with 5+ battery storage decisions, South Holland sits in the 38th percentile for approval rate (level with the England average) and the 79th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (15)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Caudwell Farm, Hollbeach - Battery Storage Facility Green Energy International · H09-0699-23 · 30 mo to decide | — | Awaiting Construction | 2026-02-03 |
Postland Road, James Road - Energy Storage System AMP Clean Energy · H02-0938-25 | 0.2 | Application Submitted | 2025-10-08 |
Fendyke Farm - Battery Energy Storage Integrum SPV 21014 Limited · H20-1007-24 · 5.3 mo to decide | 10 | Application Refused | 2025-05-13 |
Sutton Bridge Solar Farm - Walpole Battery Storage EDF Energy Renewables · H18-1077-24 · 3.5 mo to decide | — | Awaiting Construction | 2025-04-07 |
Crease Drove, Crowland - Micro Energy storage AMP Clean Energy · H02-0882-24 · 2.9 mo to decide | 0.2 | Awaiting Construction | 2025-01-13 |
Roman Bank - Energy Storage Facility AMP Energy Services Limited · H16-0565-24 · 3.5 mo to decide | 0.2 | Awaiting Construction | 2024-10-11 |
Holbeach Road - Battery Energy Storage AMP Energy Services Limited · H16-0566-24 · 2.8 mo to decide | 0.2 | Awaiting Construction | 2024-09-19 |
Whitehall-Belchmire Lane - Micro Energy Storage Facility Aggregated Micro Power Holdings Plc · H08-0469-24 · 3.7 mo to decide | 0.2 | Awaiting Construction | 2024-09-19 |
Parkside Crescent - Micro Energy Storage Facility AMP Energy Services Limited · H16-0586-24 · 2.5 mo to decide | 0.2 | Awaiting Construction | 2024-09-19 |
Boston Road - Energy Storage Facility AMP Clean Energy · H09-0597-24 · 2.3 mo to decide | 0.2 | Awaiting Construction | 2024-09-19 |
Castle Sports Complex, Albion Street - Micro Energy Storage AMP Clean Energy · H16-0621-24 · 1.9 mo to decide | 0.2 | Awaiting Construction | 2024-09-19 |
Cowbridge Road, Bicker Fen - Battery Storage AGR Solar 2 Limited · H04-0849-22 · 10.3 mo to decide | 50 | Under Construction | 2023-07-21 |
Spalding Energy Park - Battery Storage Intergen Limited · H16-1327-21 · 17.7 mo to decide | 550 | Awaiting Construction | 2023-06-14 |
Wardentree Lane - Battery Storage AMP Clean Energy · H14-0333-23 | 0.2 | Application Submitted | 2023-04-06 |
Gunthorpe Road, Marsh -Battery Storage Walpole Green Limited · 21/01442/FM · 7.2 mo to decide | — | Awaiting Construction | 2022-02-25 |
Does South Holland approve battery storage schemes?
Yes — of the 13 battery storage schemes South Holland has decided, 92% were approved (12 granted, 1 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in South Holland?
The median time from application to decision is 3.5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has South Holland consented?
601 MW has been consented across 12 approved schemes, with 10 MW refused. A further 2 applications awaits a decision.
Other technologies in South Holland
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.