Battery storage planning in South Holland

South Holland has decided 13 battery storage schemes and approved 92% of them, taking a median of 3.5 months to decide. Consented capacity: 601 MW. 2 applications still awaiting a decision.

92%
Approved
12 granted · 1 refused
3.5 mo
Median decision
UK 6 mo
601 MW
Consented
10 MW refused
2
Appeals
2 allowed on appeal

How South Holland compares

Against the 137 UK authorities with 5+ battery storage decisions, South Holland sits in the 38th percentile for approval rate (level with the England average) and the 79th percentile for speed.

Decisions by year

510Approved — 1 (2022)122Approved — 2 (2023)223Approved — 6 (2024)624Approved — 2 (2025)Refused — 1 (2025)325Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (15)

SchemeMWStatusDecided
Caudwell Farm, Hollbeach - Battery Storage Facility
Green Energy International · H09-0699-23 · 30 mo to decide
Awaiting Construction2026-02-03
Postland Road, James Road - Energy Storage System
AMP Clean Energy · H02-0938-25
0.2Application Submitted2025-10-08
Fendyke Farm - Battery Energy Storage
Integrum SPV 21014 Limited · H20-1007-24 · 5.3 mo to decide
10Application Refused2025-05-13
Sutton Bridge Solar Farm - Walpole Battery Storage
EDF Energy Renewables · H18-1077-24 · 3.5 mo to decide
Awaiting Construction2025-04-07
Crease Drove, Crowland - Micro Energy storage
AMP Clean Energy · H02-0882-24 · 2.9 mo to decide
0.2Awaiting Construction2025-01-13
Roman Bank - Energy Storage Facility
AMP Energy Services Limited · H16-0565-24 · 3.5 mo to decide
0.2Awaiting Construction2024-10-11
Holbeach Road - Battery Energy Storage
AMP Energy Services Limited · H16-0566-24 · 2.8 mo to decide
0.2Awaiting Construction2024-09-19
Whitehall-Belchmire Lane - Micro Energy Storage Facility
Aggregated Micro Power Holdings Plc · H08-0469-24 · 3.7 mo to decide
0.2Awaiting Construction2024-09-19
Parkside Crescent - Micro Energy Storage Facility
AMP Energy Services Limited · H16-0586-24 · 2.5 mo to decide
0.2Awaiting Construction2024-09-19
Boston Road - Energy Storage Facility
AMP Clean Energy · H09-0597-24 · 2.3 mo to decide
0.2Awaiting Construction2024-09-19
Castle Sports Complex, Albion Street - Micro Energy Storage
AMP Clean Energy · H16-0621-24 · 1.9 mo to decide
0.2Awaiting Construction2024-09-19
Cowbridge Road, Bicker Fen - Battery Storage
AGR Solar 2 Limited · H04-0849-22 · 10.3 mo to decide
50Under Construction2023-07-21
Spalding Energy Park - Battery Storage
Intergen Limited · H16-1327-21 · 17.7 mo to decide
550Awaiting Construction2023-06-14
Wardentree Lane - Battery Storage
AMP Clean Energy · H14-0333-23
0.2Application Submitted2023-04-06
Gunthorpe Road, Marsh -Battery Storage
Walpole Green Limited · 21/01442/FM · 7.2 mo to decide
Awaiting Construction2022-02-25

Does South Holland approve battery storage schemes?

Yes — of the 13 battery storage schemes South Holland has decided, 92% were approved (12 granted, 1 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in South Holland?

The median time from application to decision is 3.5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has South Holland consented?

601 MW has been consented across 12 approved schemes, with 10 MW refused. A further 2 applications awaits a decision.

Other technologies in South Holland

Solar in South HollandOnshore wind in South Holland

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.