Battery storage planning in Tameside

Tameside has decided 5 battery storage schemes and approved 100% of them, taking a median of 3.2 months to decide. Consented capacity: 156 MW.

100%
Approved
5 granted · 0 refused
3.2 mo
Median decision
UK 6 mo
156 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Tameside compares

Against the 137 UK authorities with 5+ battery storage decisions, Tameside sits in the 73rd percentile for approval rate (8 points above the England average) and the 83rd percentile for speed.

Decisions by year

35Approved — 1 (2018)118Approved — 2 (2022)222Approved — 1 (2023)123Approved — 1 (2025)125
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (5)

SchemeMWStatusDecided
Tudor Industrial Estate, Ashton Street- Micro Energy Storage
AMP Clean Energy · 25/00463/FUL · 3.2 mo to decide
0.2Awaiting Construction2025-09-10
Printworks Road - Stalybridge Battery Storage
Zenobe Energy · 23/00770/FUL · 3.1 mo to decide
150Awaiting Construction2023-12-15
Tame Box, Tame Street - Battery Storage
AMP Energy Services Limited · 22/00811/FUL · 1.8 mo to decide
0.2Awaiting Construction2022-10-27
Sheffield Road - Battery Storage System
FPC Electric Land Limited · 22/00110/FUL · 7.1 mo to decide
Awaiting Construction2022-09-26
Holden Way
STOR Power · 17/00846/FUL · 14.5 mo to decide
6Awaiting Construction2018-06-25

Does Tameside approve battery storage schemes?

Yes — of the 5 battery storage schemes Tameside has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Tameside?

The median time from application to decision is 3.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Tameside consented?

156 MW has been consented across 5 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Tameside

Solar in TamesideOnshore wind in Tameside

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.