Battery storage planning in Ashford
Ashford has decided 7 battery storage schemes and approved 71% of them, taking a median of 4.5 months to decide. Consented capacity: 58 MW. 3 applications still awaiting a decision.
⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Ashford compares
Against the 137 UK authorities with 5+ battery storage decisions, Ashford sits in the 5th percentile for approval rate (21 points below the England average) and the 68th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (11)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Loudon Way, Repton Park South - Battery Energy Storage Facility Amp Clean Energy · PA/2025/2065 · 1.8 mo to decide | 0.2 | Application Refused | 2026-02-13 |
Singleton Hill, Singleton - Micro Energy Storage Facility AMP Clean Energy · PA/2025/2208 | 0.2 | Application Withdrawn | 2026-01-22 |
Hornbeam Close - Micro Energy Storage AMP Clean Energy · PA/2025/2127 | 0.2 | Application Submitted | 2025-11-17 |
Cobbs Wood Industrial Estate, Chart Road - Battery Energy Storage AMP Clean Energy · PA/2025/2126 | 0.2 | Application Submitted | 2025-11-17 |
Forty Acre Wood, The Street - Battery Energy Storage System Greenfield Energy Developments Limited · PA/2025/1331 · 3 mo to decide | 300 | Application Refused | 2025-10-27 |
Sandyhurst Lane, Boughton Aluph - Energy Storage Facility AMP Clean Energy · PA/2024/2093 · 8.4 mo to decide | 0.2 | Awaiting Construction | 2025-07-23 |
Church Road, Sevington - Energy Storage Facility AMP Clean Energy · PA/2024/1999 · 4.5 mo to decide | 0.2 | Awaiting Construction | 2025-03-18 |
Stanhope Road, Kingsnorth - Micro Energy Storage Facility AMP Clean Energy · PA/2024/1998 · 4.5 mo to decide | 0.2 | Awaiting Construction | 2025-03-13 |
Ashford Road, Kingsnorth - Energy Storage Facility AMP Clean Energy · PA/2024/2022 · 2.8 mo to decide | 0.2 | Awaiting Construction | 2025-01-30 |
Stanhope Road, Kingsnorth - Micro Energy Storage Facility AMP Clean Energy · PA/2024/1998 | 0.2 | Application Submitted | 2024-10-28 |
Sellindge Substation, Church Lane - Battery Storage Pivoted Power Llp · PA/2022/2544 · 10.2 mo to decide | 57 | Awaiting Construction | 2023-08-04 |
Does Ashford approve battery storage schemes?
Yes — of the 7 battery storage schemes Ashford has decided, 71% were approved (5 granted, 2 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Ashford?
The median time from application to decision is 4.5 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Ashford consented?
58 MW has been consented across 5 approved schemes, with 300 MW refused. A further 3 applications awaits a decision.
Other technologies in Ashford
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.