Renewable planning › Battery storage › North Warwickshire
Battery storage planning in North Warwickshire
North Warwickshire has decided 8 battery storage schemes and approved 100% of them, taking a median of 7.1 months to decide. Consented capacity: 608 MW. 1 application still awaiting a decision.
How North Warwickshire compares
Against the 137 UK authorities with 5+ battery storage decisions, North Warwickshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 33rd percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (9)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Hams Hall, Hams Lane - Battery Energy Storage System Eon UK Plc · PAP/2025/0227 · 4.9 mo to decide | 98 | Awaiting Construction | 2025-10-17 |
Camp Farm, Knowle Hill - Battery Storage Ampyr Solar Europe · PAP/2024/0586 · 7.4 mo to decide | 50 | Awaiting Construction | 2025-08-18 |
Marston Fields Farm, Kingsbury Road - Battery Energy Storage PACE Wedge Energy Limited · PAP/2024/0582 · 5.9 mo to decide | 10 | Awaiting Construction | 2025-06-17 |
Marston Sewerage Pumping Station, Bodymoor Heath Lane - Battery Storage Anesco Limited · PAP/2025/0179 | 50 | Application Submitted | 2025-05-28 |
Lichfield Road, Watton Lane - Battery Storage Anglo ES Water Orton Limited · PAP/2023/0056 · 12.6 mo to decide | 49.9 | Awaiting Construction | 2024-03-05 |
Euro Car Parts - Solar Panels & Battery Storage Ivegate Limited · PAP/2023/0325 · 1.4 mo to decide | — | Awaiting Construction | 2023-10-19 |
Park Lane, Astley - Battery Energy Storage Tor Energy Solar Limited · PAP/2021/0651 · 7.9 mo to decide | — | Awaiting Construction | 2022-07-28 |
Corley Smorral Lane - Battery Storage Barrs Family Enterprises Limited · PAP/2021/0605 · 8.2 mo to decide | — | Awaiting Construction | 2022-07-27 |
Hams Hall - Battery Energy Storage System Welbar Energy Storage Limited / Penso Power (BW ESS) · PAP/2021/0473 · 6.9 mo to decide | 400 | Under Construction | 2022-03-04 |
Does North Warwickshire approve battery storage schemes?
Yes — of the 8 battery storage schemes North Warwickshire has decided, 100% were approved (8 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in North Warwickshire?
The median time from application to decision is 7.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has North Warwickshire consented?
608 MW has been consented across 8 approved schemes. A further 1 application awaits a decision.
Other technologies in North Warwickshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.