Battery storage planning in South Oxfordshire

South Oxfordshire has decided 8 battery storage schemes and approved 75% of them, taking a median of 8.9 months to decide. Consented capacity: 800 MW. 1 application still awaiting a decision.

75%
Approved
6 granted · 2 refused
8.9 mo
Median decision
UK 6 mo
800 MW
Consented
100 MW refused
2
Appeals
2 allowed on appeal

How South Oxfordshire compares

Against the 137 UK authorities with 5+ battery storage decisions, South Oxfordshire sits in the 7th percentile for approval rate (17 points below the England average) and the 21st percentile for speed.

Decisions by year

35Approved — 1 (2019)119Refused — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2024)124Approved — 2 (2025)Refused — 1 (2025)325
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (11)

SchemeMWStatusDecided
Lower road, Garsington - Energy Storage System
Net Zero Twenty One Ltd · P24/S3557/FUL · 8.9 mo to decide
100Application Refused2025-08-13
Culham Science Centre, Clifton Hampden - Battery Storage Facility
Statera Energy · P24/S1498/FUL · 14.4 mo to decide
500Awaiting Construction2025-07-22
Cowley Substation, Blackberry Lane - Battery Storage Energy System
Penso Power (BW ESS) · P24/S3405/FUL · 8.7 mo to decide
200Awaiting Construction2025-07-17
Burcot Solar Farm
Ethical Power · P23/S4132/FUL · 2.8 mo to decide
49.9Awaiting Construction2024-02-28
Burcot Farm Battery Storage
Burcot Solar Farm Limited · P23/S2095/FUL
49.9Application Withdrawn2023-11-03
Icknield Road, Ipsden - Solar Array & Battery Storage
Icknield Gas Limited · P22/S2477/FUL · 4.9 mo to decide
Awaiting Construction2022-12-15
Burcot Solar Farm
Burcot Solar Farm Limited · P22/S0960/FUL · 8.9 mo to decide
49.9Revised2022-12-06
Nuneham Courtenay Solar Farm & Battery Storage Facility
Enso Energy (Cowley Baldon Green Limited) · P20/S4360/FUL · 13.8 mo to decide
Awaiting Construction2022-01-11
Wallingford Road Energy Centre
Balance Power Projects Limited · P20/S4706/FUL · 10.9 mo to decide
Application Refused2021-11-05
Cowley electricity sub-station
Pivot Power · P19/S0623/FUL · 3.3 mo to decide
49.9Operational2019-06-04
Culham Science Centre
CESL UK Atomic Energy Authority · P16/S2368/FUL
250Abandoned2016-07-18

Does South Oxfordshire approve battery storage schemes?

Yes — of the 8 battery storage schemes South Oxfordshire has decided, 75% were approved (6 granted, 2 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in South Oxfordshire?

The median time from application to decision is 8.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has South Oxfordshire consented?

800 MW has been consented across 6 approved schemes, with 100 MW refused. A further 1 application awaits a decision.

Other technologies in South Oxfordshire

Solar in South OxfordshireOnshore wind in South Oxfordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.