Battery storage planning in West Oxfordshire

West Oxfordshire has decided 7 battery storage schemes and approved 86% of them, taking a median of 6.7 months to decide. Consented capacity: 94 MW. 6 applications still awaiting a decision.

86%
Approved
6 granted · 1 refused
6.7 mo
Median decision
UK 6 mo
94 MW
Consented
2 MW refused
0
Appeals
no appeals recorded

⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How West Oxfordshire compares

Against the 137 UK authorities with 5+ battery storage decisions, West Oxfordshire sits in the 23rd percentile for approval rate (6 points below the England average) and the 39th percentile for speed.

Decisions by year

35Approved — 2 (2021)221Approved — 1 (2023)123Approved — 3 (2025)Refused — 1 (2025)425
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (14)

SchemeMWStatusDecided
Tar Solar Farm
Bluefield Renewable Developments Limited · 24/03261/FUL · 7.6 mo to decide
40Awaiting Construction2025-09-05
Akeman Solar Park & Battery Storage
British Solar Renewables · 25/00234/FUL · 5.8 mo to decide
1.5Application Refused2025-08-28
Quarry Solar Farm & Battery Storage Facility
JBM Solar Projects 34 Limited · 24/01565/FUL · 13 mo to decide
35Awaiting Construction2025-07-28
Aston Road, Aston - Solar Panels & Battery Energy Storage System
Ampyr Solar Europe · 25/01702/FUL
40Application Submitted2025-07-25
Witney Bypass, Stanton Harcourt Road - Battery Storage
Voltwise Power Holdings Limited · 25/01656/FUL
150Application Submitted2025-07-25
Eynsham Fire Station, Old Station Way - Micro Energy Storage
AMP Energy Services Limited · 25/00324/FUL · 2.6 mo to decide
0.2Awaiting Construction2025-05-07
Caswell Lane, Brize Norton - Solar Farm & Battery Storage
Ampyr Solar Europe · 24/03278/FUL
30Application Submitted2025-01-30
Akeman Solar Park & Battery Storage
British Solar Renewables · 23/02917/FUL · 3 mo to decide
1.5Revised2024-02-05
Shilton Road - Solar Park & Battery Storage
Ecotricity Generation Limited · 22/02472/FUL · 9.6 mo to decide
Awaiting Construction2023-06-27
Quarry Solar Farm & Battery Storage Facility
JBM Solar Projects 34 Limited · 23/01524/FUL
Revised2023-06-02
Akeman Solar Park & Battery Storage
British Solar Renewables · 21/02473/FUL
1.5Revised2022-08-10
Aurora Solar Farm
Low Carbon UK Solar Investment Company · 19/02516/FUL · 18.9 mo to decide
18Under Construction2021-04-22
Blenheim Net Zero Estate
Vanburgh Unit Trust · 20/01817/FUL · 4.9 mo to decide
1Awaiting Construction2021-01-08
Ventura Park
British Solar Renewables · 17/03531/FUL
7Abandoned2017-10-27

Does West Oxfordshire approve battery storage schemes?

Yes — of the 7 battery storage schemes West Oxfordshire has decided, 86% were approved (6 granted, 1 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in West Oxfordshire?

The median time from application to decision is 6.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has West Oxfordshire consented?

94 MW has been consented across 6 approved schemes, with 2 MW refused. A further 6 applications awaits a decision.

Other technologies in West Oxfordshire

Solar in West OxfordshireOnshore wind in West Oxfordshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.