Battery storage planning in East Hertfordshire
East Hertfordshire has decided 5 battery storage schemes and approved 100% of them, taking a median of 19.9 months to decide. Consented capacity: 465 MW. 4 applications still awaiting a decision.
⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How East Hertfordshire compares
Against the 137 UK authorities with 5+ battery storage decisions, East Hertfordshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 1st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (9)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Standon Hill, Puckeridge - Battery Energy Storage Facility AMP Clean Energy · 3/26/0113/FUL | 0.2 | Application Submitted | 2026-02-12 |
Ware Solar Park - Solar Farm & Battery Energy Storage The Farm Energy Company · 3/24/1275/FUL · 15.2 mo to decide | 5 | Awaiting Construction | 2025-10-17 |
Greens Farm - Battery energy storage Cambridge Power · 3/21/0969/FUL · 50.4 mo to decide | 50 | Awaiting Construction | 2025-07-18 |
Dellows, Ginns Road - Battery Storage Grenergy Renewables UK Limited · 3/25/0917/FUL | 90 | Application Submitted | 2025-06-24 |
Ginns Road, Stocking Pelham - Battery Energy Storage FRV TH Powertek Limited · 3/24/1953/FUL · 5.8 mo to decide | 400 | Awaiting Construction | 2025-04-29 |
Beane Solar Farm - Solar Panels Renewable Energy Systems RES ltd (Beaufort) · 3/24/2245/FUL | 354 | Application Submitted | 2024-12-20 |
Wickham Hall Estate - Battery Storage Endurance Energy Wickham Hall Limited · 3/21/2601/FUL · 24.6 mo to decide | — | Awaiting Construction | 2023-12-19 |
Stocking Pelham - Battery Storage System Renewable Connections · 3/22/0806/FUL | 50 | Application Submitted | 2022-04-27 |
Hadham Road Private Developer · 3/17/2959/FUL | 10 | Planning Permission Expired | 2017-12-22 |
Does East Hertfordshire approve battery storage schemes?
Yes — of the 5 battery storage schemes East Hertfordshire has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in East Hertfordshire?
The median time from application to decision is 19.9 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has East Hertfordshire consented?
465 MW has been consented across 5 approved schemes. A further 4 applications awaits a decision.
Other technologies in East Hertfordshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.