Battery storage planning in Vale of White Horse

Vale of White Horse has decided 5 battery storage schemes and approved 100% of them, taking a median of 4 months to decide. Consented capacity: 300 MW. 4 applications still awaiting a decision.

100%
Approved
5 granted · 0 refused
4 mo
Median decision
UK 6 mo
300 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Vale of White Horse compares

Against the 137 UK authorities with 5+ battery storage decisions, Vale of White Horse sits in the 73rd percentile for approval rate (8 points above the England average) and the 73rd percentile for speed.

Decisions by year

35Approved — 2 (2023)223Approved — 1 (2024)124Approved — 2 (2025)225
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Snowswick Lane, Coleshill - Solar Farm
Abei Energy Limited · P25/V1646/FUL
25Application Submitted2025-08-20
Sandford Lane, Kennington - Battery Energy Storage
Cowley Energy Reserve 2 Limited · P25/V1800/FUL
Application Submitted2025-08-19
Appleford - Battery Energy Storage
TBC 001 Limited · P25/V0149/FUL · 6.3 mo to decide
300Awaiting Construction2025-08-08
The Sutton Courtenay Waste Management Site, Appleford Sidings
Development at Sutton Courtenay Waste Management · P25/V1204/CM · 1.3 mo to decide
Awaiting Construction2025-07-18
Willowfields Energy Park, Marcham - Battery Energy Storage
Exagen Development Limited · P24/V2698/FUL
20Application Submitted2024-12-18
Barnstaples Farm
Nextpower SPV 14 Limited · P21/V3395/FUL · 46.6 mo to decide
Awaiting Construction2024-02-28
Westmill Farm - Battery Storage
Private Developer · P23/V2003/O · 1.8 mo to decide
Awaiting Construction2023-11-07
Radley College, Kennington Gate - Solar Array & Battery Storage
Radley College · P23/V0861/FUL · 4 mo to decide
Awaiting Construction2023-08-10
Appleford Sidings, Sutton Courtenay - Battery Storage
Infinis Solar Developments Limited · MW.0069/21
Application Submitted2021-05-19

Does Vale of White Horse approve battery storage schemes?

Yes — of the 5 battery storage schemes Vale of White Horse has decided, 100% were approved (5 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a battery storage scheme application take in Vale of White Horse?

The median time from application to decision is 4 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Vale of White Horse consented?

300 MW has been consented across 5 approved schemes. A further 4 applications awaits a decision.

Other technologies in Vale of White Horse

Solar in Vale of White HorseOnshore wind in Vale of White Horse

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.