Battery storage planning in Rotherham

Rotherham has decided 14 battery storage schemes and approved 100% of them, taking a median of 3.2 months to decide. Consented capacity: 520 MW. 6 applications still awaiting a decision.

100%
Approved
14 granted · 0 refused
3.2 mo
Median decision
UK 6 mo
520 MW
Consented
across approved schemes
2
Appeals
2 allowed on appeal

How Rotherham compares

Against the 137 UK authorities with 5+ battery storage decisions, Rotherham sits in the 73rd percentile for approval rate (8 points above the England average) and the 83rd percentile for speed.

Decisions by year

35Approved — 2 (2017)217Approved — 1 (2018)118Approved — 3 (2022)322Approved — 3 (2023)323Approved — 2 (2025)225Approved — 1 (2026)126
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (20)

SchemeMWStatusDecided
Thurcroft Battery Storage, Green Lane - Battery Energy Storage System
HC ESS7 LIMITED · RB2025/1556 · 2.1 mo to decide
Awaiting Construction2026-01-30
Moat Lane, Wickersley - Battery Storage Facility
Newton Energi Limited · RB2024/0063 · 28.3 mo to decide
100Awaiting Construction2025-11-19
Moat Lane, Wickersley - Battery Storage Facility
Harmony Energy Storage · RB2024/0321 · 20.9 mo to decide
100Awaiting Construction2025-11-19
Maltby Solar Farm
Infinis Energy Services Limited · 25/01554/FULM
50Application Submitted2025-08-01
Thurcroft Interchange Energy Park - Battery Energy Storage System
Exagen · RB2025/0714
50Application Submitted2025-06-06
Hard Lane, Kiveton Park - Battery Energy Storage System
Harmony Energy · RB2025/0240
Application Submitted2025-02-17
New South Farm, Piper Lane - Solar Farm
Abei Energy Group · RB2025/0029
11.97Application Submitted2024-12-24
Brinsworth Road, Brinsworth - Battery Energy storage
Root Power South Limited · RB2024/1307
40Application Submitted2024-09-09
Chesterfield Road, Swallownest - Battery Energy Storage
Conrad Energy Developments Ii Limited · RB2023/1323
Application Submitted2023-09-22
Claire Court, Rawmarsh Road - Battery Energy Storage Facility
Conrad Energy (Developments) Ii Limited · RB2023/0542 · 2.1 mo to decide
40Awaiting Construction2023-06-20
Common Farm - Solar Farm & Battery Storage
Banks Renewable · RB2022/1203 · 10.3 mo to decide
49Awaiting Construction2023-06-13
Green Lane, Thurcroft - Battery Energy Storage Facility
Newton Energi Limited · RB2022/1767 · 5.5 mo to decide
85Awaiting Construction2023-05-12
Aven Industrial Park, Tickhill Road - Battery Storage
Power Initiatives Limited · RB2022/1267 · 1.8 mo to decide
Awaiting Construction2022-09-28
West Melton Electricity Substation - Energy Storage System
Brampton Energy Storage Limited · RB2022/0853 · 3.6 mo to decide
26Awaiting Construction2022-09-13
Magna Way, Templeborough - Battery Energy Storage Facility
Newton Energi · RB2022/0622 · 2 mo to decide
Awaiting Construction2022-06-21
Aven Industrial Estate
Max Design Consultancy · RB2017/0910 · 12.1 mo to decide
20Planning Permission Expired2018-06-19
Nether Moor Field
Thurcroft Energy (Max Design Consultancy) · RB2017/1426 · 2.7 mo to decide
49.9Operational2017-12-21
Swangate Project - Energy Storage System
Econergy International Limited · RB2017/1132 · 2 mo to decide
50Awaiting Construction2017-09-22
Thrybergh Hydroelectric Scheme
Barn Energy · RB2016/1468
0.3Operational2016-11-03
Maltby / CLNR EES1
Northern Powergrid
0.1Decommissioned2005-05-05

Does Rotherham approve battery storage schemes?

Yes — of the 14 battery storage schemes Rotherham has decided, 100% were approved (14 granted, 0 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Rotherham?

The median time from application to decision is 3.2 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Rotherham consented?

520 MW has been consented across 14 approved schemes. A further 6 applications awaits a decision.

Other technologies in Rotherham

Solar in RotherhamOnshore wind in Rotherham

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.