Renewable planning › Battery storage › Medway
Battery storage planning in Medway
Medway has decided 7 battery storage schemes and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 300 MW.
⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Medway compares
Against the 137 UK authorities with 5+ battery storage decisions, Medway sits in the 73rd percentile for approval rate (8 points above the England average) and the 97th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (8)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Cloverlay Industrial Park, Canterbury Lane - Micro Energy Storage System AMP Clean Energy · MC/25/2400 | 0.2 | Application Withdrawn | 2026-02-18 |
Featherby Road, Bredgar Road - Micro Energy Storage AMP Clean Energy · MC/25/2401 · 1.8 mo to decide | 0.2 | Awaiting Construction | 2026-02-05 |
Power Station Road, Isle Of Grain - Battery Energy Storage Ecostor Grain West Limited · MC/25/1338 · 5.4 mo to decide | 249 | Awaiting Construction | 2025-12-12 |
Four Elms Roundabout, Wainscott - Micro Energy Storage AMP Clean Energy · MC/25/1433 · 1.7 mo to decide | 0.2 | Awaiting Construction | 2025-09-05 |
Beechings Way, Eastcourt Lane - Battery Energy Storage System AMP Clean Energy · MC/25/1432 · 1.7 mo to decide | — | Awaiting Construction | 2025-09-05 |
Medway One - Energy Hub Low Carbon Limited · MC/24/0489 · 3.9 mo to decide | — | Awaiting Construction | 2024-07-04 |
Mid Kent College Medway Campus, Medway Road - Battery Storage, ASHP Mid Kent College · MC/23/2594 · 0 mo to decide | 1 | Awaiting Construction | 2023-11-23 |
Sundridge Hill RNA Energy · MC/17/3770 · 9.1 mo to decide | 49.5 | Under Construction | 2018-08-17 |
Does Medway approve battery storage schemes?
Yes — of the 7 battery storage schemes Medway has decided, 100% were approved (7 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Medway?
The median time from application to decision is 1.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Medway consented?
300 MW has been consented across 7 approved schemes. There are no applications currently awaiting a decision.
Other technologies in Medway
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.