Renewable planning › Battery storage › Shropshire
Battery storage planning in Shropshire
Shropshire has decided 15 battery storage schemes and approved 100% of them, taking a median of 3.8 months to decide. Consented capacity: 114 MW. 7 applications still awaiting a decision.
How Shropshire compares
Against the 137 UK authorities with 5+ battery storage decisions, Shropshire sits in the 73rd percentile for approval rate (8 points above the England average) and the 76th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (22)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Rednal Airfield, West Felton - Battery Energy Storage Private Developer · 25/01250/FUL | 300 | Application Submitted | 2025-05-07 |
Pelham Road, Upton Magna - Battery Energy Storage System Elgin Energy Esco Limited · 25/01638/FUL | 100 | Application Submitted | 2025-05-01 |
Buildwas - Battery Energy Storage Greenfield Energy Developments Limited · 25/01270/FUL | 100 | Application Submitted | 2025-04-14 |
Battery Shrewsbury Substation, Uffington - Battery Energy Storage Lower 48 Energy BESS Limited · 25/00531/FUL | 100 | Application Submitted | 2025-02-24 |
Steventon Road - Battery Energy Storage Greenfield Company · 24/02223/FUL · 2.3 mo to decide | 23 | Awaiting Construction | 2024-08-30 |
Bath Mews, Minsterley - Battery Storage Facility Fig Power · 24/00889/FUL · 4.2 mo to decide | 10 | Awaiting Construction | 2024-07-26 |
Farr & Harris - Energy Storage Facility Aggregated Micro Power Holdings Plc · 24/00510/FUL · 1.4 mo to decide | 0.2 | Awaiting Construction | 2024-03-22 |
Brassey Road - Micro Energy Storage Facility AMP Energy Services Limited · 24/00492/FUL · 1.4 mo to decide | 0.2 | Awaiting Construction | 2024-03-22 |
Albrighton Substation, Beamish Lane - Battery Storage Fig Power (part of Hydrock) · 23/04541/FUL · 3.8 mo to decide | 7 | Awaiting Construction | 2024-02-26 |
Hollydale, Buildwas Road - Battery Storage Telford Four Limited · TWC/2023/0144 · 10.4 mo to decide | 40 | Awaiting Construction | 2024-01-12 |
Rock Farm - Solar Farm Enviromena · 22/05424/EIA · 9.8 mo to decide | 12 | Awaiting Construction | 2023-09-25 |
Pepperhill Solar Farm - Solar Farm & Battery Storage Low Carbon · 22/03068/FUL · 10.5 mo to decide | — | Operational | 2023-06-07 |
Hollins Lane - Battery Energy Storage Hydrock Consultants Limited · 23/00223/FUL · 3.9 mo to decide | 13 | Awaiting Construction | 2023-05-17 |
Bridge Farm, Uffington - Battery Energy Storage Hydrock · 23/00254/FUL · 2.7 mo to decide | 8 | Awaiting Construction | 2023-04-19 |
Albrighton Substation, Beamish Lane - Battery Storage Fig Power · 22/05043/FUL | 7 | Revised | 2023-04-12 |
Cold Move, Maes-Y-Clawdd Cold Move Limited · 23/00031/FUL · 1.6 mo to decide | 1 | Awaiting Construction | 2023-04-05 |
County Lane - Solar farm Boultbee Brooks Renewable Energy Limited · 22/01816/FUL · 11.2 mo to decide | — | Awaiting Construction | 2023-03-21 |
Bath Mews, Minsterley - Battery Storage Facility Hydrock Consultants Limited · 23/01031/FUL | 10 | Revised | 2023-03-09 |
Bath Mews, Minsterley - Battery Storage Facility Hydrock Consultants Limited · 22/01897/FUL | 10 | Revised | 2022-11-01 |
Cefn-Y-Maes Farm, Rhydycroesau - Solar Park Positech Energy Limited · 22/03447/FUL · 2.6 mo to decide | — | Awaiting Construction | 2022-10-14 |
Bubney Farm AlphaReal · 21/01661/FUL · 6 mo to decide | — | Operational | 2021-10-01 |
Albrighton Solar farm Big60Million/Belectric · 15/02787/FUL · 0.3 mo to decide | — | Operational | 2015-12-14 |
Does Shropshire approve battery storage schemes?
Yes — of the 15 battery storage schemes Shropshire has decided, 100% were approved (15 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Shropshire?
The median time from application to decision is 3.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Shropshire consented?
114 MW has been consented across 15 approved schemes. A further 7 applications awaits a decision.
Other technologies in Shropshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.
Novarly Parcel · official public data, read properly · parcel.novarly.com