Battery storage planning in Doncaster
Doncaster has decided 10 battery storage schemes and approved 100% of them, taking a median of 5.1 months to decide. Consented capacity: 4,132 MW. 6 applications still awaiting a decision.
How Doncaster compares
Against the 137 UK authorities with 5+ battery storage decisions, Doncaster sits in the 73rd percentile for approval rate (8 points above the England average) and the 61st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (17)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Butt Lane, Hooton Pagnell Battery Energy Storage British Solar Renewables · 25/02389/FULM | 30 | Application Submitted | 2025-12-05 |
Moorhouse Grange, Moorhouse Lane - Battery Energy Zetland Group · 25/01535/FULM | — | Application Submitted | 2025-08-22 |
Aggreko UK, Sandall Stones Road - Battery Energy Storage Aggreko UK Limited · 25/00936/FUL · 2.6 mo to decide | — | Awaiting Construction | 2025-07-31 |
Thorpe Marsh Power Station, Marsh Lane - Battery Energy Storage West Burton Energy / Banks Group · 23/00537/FULM · 21.9 mo to decide | 1400 | Awaiting Construction | 2025-01-28 |
Thorpe Marsh Power Station - Battery Energy Storage West Burton Energy · 23/00537/FULM · 21.9 mo to decide | 1450 | Awaiting Construction | 2025-01-28 |
Cutts Bros, Wharf Road - Battery Storage Facility Newton Energi Limited · 24/00841/FUL · 5.1 mo to decide | 50 | Awaiting Construction | 2024-10-29 |
The Balk, Almholme - Energy Storage System Innova Renewables · 23/02482/FULM · 10.5 mo to decide | 1025 | Awaiting Construction | 2024-10-14 |
Fordtead Lane, Thorpe Marsh - Battery Energy Facility Newton Energi Limited · 23/01746/FULM · 7.6 mo to decide | 180 | Awaiting Construction | 2024-04-30 |
Cutts Bros, Wharf Road - Battery Storage Facility Newton Energi Limited · 23/01843/FUL · 1.6 mo to decide | 50 | Revised | 2023-12-12 |
J3 Business Park - Battery Storage Facility Forepower Limited · 23/01072/FUL · 1.5 mo to decide | 16 | Awaiting Construction | 2023-07-11 |
Thorpe Marsh Power Station - Battery Energy Storage West Burton Energy · 23/00022/FULM | 1450 | Revised | 2023-01-26 |
J3 Business Park - Battery Energy Storage Facility Forepower Limited · 22/02368/FUL · 3 mo to decide | 10 | Under Construction | 2023-01-24 |
Mere Flats Solar Farm NextPower UK · 22/01978/FULM | 16 | Application Submitted | 2022-08-22 |
Woodlands - Battery Energy Storage Infinis Battery Storage Limited · 22/00806/FUL · 3.4 mo to decide | 1.2 | Awaiting Construction | 2022-07-11 |
Warren Farm Solar Farm & Battery Storage Enso Green Holdings I Limited · 21/02567/FULM · 6.9 mo to decide | — | Awaiting Construction | 2022-03-15 |
Long Lands Lane Tiger Energy · 17/02562/FUL | 12 | Abandoned | 2017-10-16 |
J3 Business Park Car Hill Power · 16/02055/FUL | 1 | Revised | 2016-08-12 |
Does Doncaster approve battery storage schemes?
Yes — of the 10 battery storage schemes Doncaster has decided, 100% were approved (10 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in Doncaster?
The median time from application to decision is 5.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Doncaster consented?
4,132 MW has been consented across 10 approved schemes. A further 6 applications awaits a decision.
Other technologies in Doncaster
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.