King's Lynn and West Norfolk has decided 15 battery storage schemes and approved 100% of them, taking a median of 6.7 months to decide. Consented capacity: 922 MW. 4 applications still awaiting a decision.
How King's Lynn and West Norfolk compares
Against the 137 UK authorities with 5+ battery storage decisions, King's Lynn and West Norfolk sits in the 73rd percentile for approval rate (8 points above the England average) and the 39th percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (19)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Land Adjacent to Walpole National Grid Substation - Battery Energy Storage STP Green Limited · 24/01275/FM · 14.3 mo to decide | — | Awaiting Construction | 2025-11-06 |
Sluice Road, Wiggenhall St Germans - Solar Array & Battery Storage Power Different Limited · 25/01267/FM · 2.1 mo to decide | — | Awaiting Construction | 2025-10-08 |
Walsoken, Burrettgate Road - Battery Storage Facility Walsoken Limited · 23/02302/FM · 18.9 mo to decide | 200 | Awaiting Construction | 2025-07-25 |
High Road, Saddlebow - Battery Storage Lynn Power Limited · 22/01151/FM · 24.7 mo to decide | 50 | Awaiting Construction | 2024-07-29 |
Sandringham Estate - Battery Storage Facility Royal Sandringham Estate · 24/00562/F · 3.1 mo to decide | — | Awaiting Construction | 2024-07-12 |
Meerdyke Solar Panels & Battery Storage Downing Renewable Developments Llp · 22/01987/FM · 15.6 mo to decide | — | Awaiting Construction | 2024-03-06 |
Burrettgate Road - Battery Storage Facility Mercia Power Response Limited · 23/00941/F | — | Revised | 2023-09-13 |
Sedgeford Hall Estate - Solar Panels & Battery Storage Regener8 Power · 22/00704/FM · 15.8 mo to decide | — | Awaiting Construction | 2023-08-23 |
Walpole Sub Station, Walpole Bank - Battery Storage Henry Energy Limited · 22/02021/F · 7.8 mo to decide | 100 | Awaiting Construction | 2023-07-04 |
Walpole Sub Station, Walpole Bank - Battery Storage Henry Energy Limited · 22/02265/FM | 100 | Application Submitted | 2022-12-21 |
Walpole Bank - Battery Energy Storage Facility Field Devco Limited · 22/02021/FM | 100 | Application Submitted | 2022-11-08 |
Walpole St Andrew - Battery storage Alfred Energy Limited · 22/00438/FM · 6.7 mo to decide | 100 | Awaiting Construction | 2022-09-20 |
North Walpole, St Peter - Battery Energy Storage Roc Noir Limited · 21/01803/FM · 8.3 mo to decide | 100 | Awaiting Construction | 2022-06-10 |
Hall Farm, West End Northwold - Solar Farm Ampyr Solar Europe · 21/02302/FM · 3.1 mo to decide | 7.5 | Operational | 2022-03-15 |
Model Farm Tribus Clean Energy · 21/01715/FM · 4.9 mo to decide | 49.9 | Awaiting Construction | 2022-01-27 |
Estuary Farm, Edward Benefer Way - Solar Farm & Battery Storage Namene Solar · 21/01432/FM · 4.8 mo to decide | 15 | Awaiting Construction | 2021-12-08 |
Lapwing Fen 2 - Battery Storage Plant Tribus Clean Energy · 19/02004/FM · 5.1 mo to decide | 250 | Under Construction | 2020-04-27 |
Lapwing Fen II, Crown Farm Private Developer · 19/02002/FM · 3.3 mo to decide | 49.9 | Awaiting Construction | 2020-03-05 |
Model Farm Tribus Clean Energy · 19/02003/F | 49.9 | Revised | 2019-11-20 |
Does King's Lynn and West Norfolk approve battery storage schemes?
Yes — of the 15 battery storage schemes King's Lynn and West Norfolk has decided, 100% were approved (15 granted, 0 refused). The UK-wide rate for battery storage is 92%.
How long does a battery storage scheme application take in King's Lynn and West Norfolk?
The median time from application to decision is 6.7 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has King's Lynn and West Norfolk consented?
922 MW has been consented across 15 approved schemes. A further 4 applications awaits a decision.
Other technologies in King's Lynn and West Norfolk
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.