Battery storage planning in Liverpool

Liverpool has decided 9 battery storage schemes and approved 100% of them, taking a median of 6.8 months to decide. Consented capacity: 166 MW.

100%
Approved
9 granted · 0 refused
6.8 mo
Median decision
UK 6 mo
166 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Liverpool compares

Against the 137 UK authorities with 5+ battery storage decisions, Liverpool sits in the 73rd percentile for approval rate (8 points above the England average) and the 37th percentile for speed.

Decisions by year

35Approved — 1 (2019)119Approved — 1 (2020)120Approved — 1 (2021)121Approved — 5 (2025)525
Approved Refused

Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (9)

SchemeMWStatusDecided
Jeffrey Humble Playing Fields, Long Lane - Micro Energy Storage System
AMP Clean Energy · 25F/2009 · 1.5 mo to decide
0.2Awaiting Construction2025-09-16
Leisure United Simpson - Micro Energy Storage System
AMP Clean Energy · 25F/2003 · 1.5 mo to decide
0.2Awaiting Construction2025-09-16
Leisure United Jericho Lane - Micro Energy Storage System
AMP Clean Energy · 25F/1634 · 1.8 mo to decide
0.2Awaiting Construction2025-08-26
Lister Battery Limited - Battery Energy Storage System
Lister Battery Limited · 24F/2904 · 5 mo to decide
6Awaiting Construction2025-04-23
Speke Hall Avenue - Battery Energy Storage System
Beryl Street Generation Limited · 23F/3121 · 13.8 mo to decide
Awaiting Construction2025-02-11
Lister Drive
Arenko Cleantech / Stratcraft · 20F/0335 · 12.9 mo to decide
49.9Operational2021-03-02
Liverpool Energy Management Facility
Statkraft UK · 20F/0550 · 8.6 mo to decide
49.9Operational2020-11-10
Carnegie Road (Phase 2)
Shawton Engineering · 19F/0626 · 8.7 mo to decide
40Planning Permission Expired2019-12-01
Land at Carnegie Road
�rsted · 16F/2680
20Operational2016-11-01

Does Liverpool approve battery storage schemes?

Yes — of the 9 battery storage schemes Liverpool has decided, 100% were approved (9 granted, 0 refused). The UK-wide rate for battery storage is 92%.

How long does a battery storage scheme application take in Liverpool?

The median time from application to decision is 6.8 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much battery storage capacity has Liverpool consented?

166 MW has been consented across 9 approved schemes. There are no applications currently awaiting a decision.

Other technologies in Liverpool

Solar in LiverpoolOnshore wind in Liverpool

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.