Renewable planning › Battery storage › Calderdale
Battery storage planning in Calderdale
Calderdale has decided 6 battery storage schemes and approved 100% of them, taking a median of 5.1 months to decide. Consented capacity: 645 MW. 2 applications still awaiting a decision.
⚠️ Small caseload (6 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Calderdale compares
Against the 137 UK authorities with 5+ battery storage decisions, Calderdale sits in the 73rd percentile for approval rate (8 points above the England average) and the 61st percentile for speed.
Decisions by year
Battery storage decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (9)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Holmfield Industrial Estate - Energy Storage Facility Smith Brothers Holmfield BESS Limited · 24/02801/FUL · 15.7 mo to decide | — | Awaiting Construction | 2025-10-28 |
Holmfield Battery Storage Masdar Arlington Energy · 24/01306/FUL · 5.3 mo to decide | 500 | Awaiting Construction | 2025-05-29 |
Ashday Hall Farm, Ashday Lane - Battery Energy Storage Sandbrook Capital Bes Limited · 24/00680/FUL · 7.1 mo to decide | 65 | Awaiting Construction | 2025-03-12 |
Lowfields Energy Storage Project UK Battery Storage · 22/01356/FUL · 2.6 mo to decide | 49.9 | Awaiting Construction | 2023-03-03 |
Stainland Road, Salterhebble - Battery Storage Facility Whirlwind Energy Storage Limited · 21/00839/FUL · 3.5 mo to decide | 25 | Awaiting Construction | 2021-09-28 |
Elland Storage Project UK Battery Storage · 20/01226/FUL | 49.9 | Revised | 2020-10-14 |
Swales Moor Farm Bouygues Energies · 20/00240/FUL · 5 mo to decide | 5 | Planning Permission Expired | 2020-08-13 |
Elland Storage Project UK Battery Storage · 18/00478/192 | 49.9 | Revised | 2018-04-17 |
Stainland Road Sterling Power Group · 16/01216/FUL | 20 | Application Withdrawn | 2018-02-08 |
Does Calderdale approve battery storage schemes?
Yes — of the 6 battery storage schemes Calderdale has decided, 100% were approved (6 granted, 0 refused). The UK-wide rate for battery storage is 92%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a battery storage scheme application take in Calderdale?
The median time from application to decision is 5.1 months, against a UK median of 6 months for battery storage. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much battery storage capacity has Calderdale consented?
645 MW has been consented across 6 approved schemes. A further 2 applications awaits a decision.
Other technologies in Calderdale
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.